An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Headquarters SNF/HLW Integration Meeting Mark Arenaz November 8, 2005

  2. Meeting Objective • Discuss issues facing EM concerning the storage, packaging, transportation and disposal of SNF and HLW • Ensure common understanding by Headquarters and the Field Offices • Reach decisions to the extent possible • Identify a path forward for making a decision on outstanding issues with assigned actions • Identify Headquarters actions where needed

  3. Meeting Attendees • Participants included: • RW-1, Paul Golan • RW, Chris Kouts and Markus Popa • NE, Joe Boda • EM-2, Charlie Anderson • EM 10 Cynthia Anderson and staff • National Spent Nuclear Fuel Program • Hanford • Idaho • Savannah River • West Valley

  4. Issues • Integrated Acceptance Schedule • Agreement on assumption and methodology • Site visits • Completed IAS by March • SNF disposal paths • Cancel melt and dilute ROD • Use a combination of H-canyon and direct disposal • Evaluate the fuel swap between Idaho & SRS

  5. Issues • Need/timing of packaging and shipping capabilities • Hanford - execute current plan • Idaho – Review Idaho Dry Storage Project • SRS – Evaluate swap with continued use of H Canyon • Disposal of calcine • New cost estimate for vitrification • Evaluate canisterization

  6. Issues • Disposition of sodium-bonded SNF • Fermi-1 blanket • FFTF SNF • Disposition of Cs/Sr capsules • Evaluate disposal options

  7. Issues • Disposition of contact handled – unirradiated materials • Sites provide input on orphans • West Valley material disposal • Miscellaneous debris and fines in processing cell

  8. Conclusions • Very successful meeting • Action items are being tracked • Next meeting planned in six months