Adoption of the FY 2019 - 2023 Capital Improvement Program Budget

Adoption of the FY 2019 - 2023 Capital Improvement Program Budget. May 7, 2018. Recommendation. Find proposed actions are not “projects” as defined in CEQA & are not subject to environmental review Adopt by resolution the City’s FY 2019 – 2023 Capital Improvement Program (CIP) Budget.

kaym
Download Presentation

Adoption of the FY 2019 - 2023 Capital Improvement Program Budget

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Adoption of the FY 2019 - 2023 Capital Improvement Program Budget May 7, 2018

  2. Recommendation • Find proposed actions are not “projects” as defined in CEQA & are not subject to environmental review • Adopt by resolution the City’s FY 2019 – 2023 Capital Improvement Program (CIP) Budget

  3. Highlights • 203 active projects with estimated cost of $1.3B • $788.2M appropriated to date • $83.5M recommended for appropriation • 97 projects recommended for funding • 25 new projects

  4. Changes to FY 2019 CIP 13 budget adjustments have been made during the CIP budget hearings that differ from the printed Recommended FY 2019 CIP budget document • These changes have been incorporated into the budget & are reflected in Exhibit B

  5. Changes to FY 2019 CIP • Colorado Street Bridge – Suicide Mitigation Enhancements – Design Phase • Add new project & appropriate $400K in General Fund reserves • Provides for installation of vertical barrier treatments along both sides & each end of the Colorado Street Bridge • Preparation of environmental document & design phase will begin in FY 2019 & be completed in FY 2020

  6. Changes to FY 2019 CIP • YWCA Building Closure & Protection • Added project back into CIP & increased the total estimated project cost to $1M • Expanded the scope to include structural shoring of the building • Construction bid significantly higher than anticipated & will be completed when funding is identified

  7. Changes to FY 2019 CIP • Annual ADA Sidewalk Improvement Program • Appropriate $400K in CDBG funds • Several changes occurred which allow this project to be awarded $400K in CDBG • Congress increased City’s allotment for FY 2019 by $200K • $100K project slated for PUSD was canceled • Staff recently identified unallocated funds of approximately $100K • CDBG PY 18-19 Action Plan will be presented to City Council on May 21, 2018 • This funding will allow for additional sidewalk improvements in NW Pasadena

  8. Changes to FY 2019 CIP • Annual Citywide Street & ADA Improvement Program • Reduce recommended appropriation to $1.99M in RMRA(SB1) funds • Work plan revised to reflect reduced appropriation • Design of approximately 3.4 miles of resurfacing will be completed & construction will begin • Traffic Signal at Garfield Avenue & Washington Boulevard • Appropriate $400K in RMRA (SB1) & $146K in Measure M • Construction will begin in FY 2019

  9. Changes to FY 2019 CIP • Traffic Signal at Orange Grove Boulevard & Craig Avenue • Appropriate $60K in Measure M • Design will be completed in FY 2019 • Traffic Signal at Fair Oaks Avenue & Bellevue Street • Appropriate $75K in Measure M • Design will be completed in FY 2019

  10. Changes to FY 2019 CIP • Traffic Signal at Orange Grove Boulevard & Sunnyslope Avenue • Move from future to active projects • Appropriate $65K in Measure M • Design will be completed in FY 2019 • Concrete Traffic Signal/Street Lighting Pole Replacement – Phase 1 • Appropriate $50K in Measure M • Increase scope of work to include replacement of concrete traffic signal pole at Arroyo Parkway & Green Street

  11. Changes to FY 2019 CIP • Conductor Replacement & Testing • Appropriate $1.2M in Underground Utilities Fund • Remove the $1.2M in Power Bond • Addresses replacements & repairs to assets previously converted from overhead to underground utilities • Power Distribution Capacity & Reliability Program • Appropriate $2.2M in Underground Utilities Fund • Remove $2.2M in Power Bond • Addresses replacements & repairs to assets previously converted from overhead to underground utilities

  12. Changes to FY 2019 CIP • Replacement & Upgrade of Electrical Substructures • Appropriate $1M in Underground Utilities Fund • Remove $1M in Power Bond • Addresses replacements & repairs to assets previously converted from overhead to underground utilities • Distribution System Expansion • Appropriate $1.1M in Underground Utilities Fund • Remove $1.1M in Power Bond • Addresses new construction related to underground utilities expansion

  13. Fiscal Impact • Approval of City Manager’s Recommended CIP budget & proposed revisions outlined in report will establish FY 2019 – 2023 CIP • Total appropriation $83,455,880