FAIR Status Report Hans Ströher NuPECC-Meeting Cracow June 9, 2006

FAIR Status Report Hans Ströher NuPECC-Meeting Cracow June 9, 2006. FAIR Baseline Technical Report 2006 Volume 1: Executive Summary Volume 2: Technical Report Accelerators and Scientific Infrastructure ~ 700 pages Volume 3: Technical Experiment Proposals on QCD Physics

kuniko
Download Presentation

FAIR Status Report Hans Ströher NuPECC-Meeting Cracow June 9, 2006

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FAIR Status Report Hans Ströher NuPECC-Meeting Cracow June 9, 2006

  2. FAIR Baseline Technical Report 2006 Volume 1: Executive Summary Volume 2: Technical Report Accelerators and Scientific Infrastructure ~ 700 pages Volume 3: Technical Experiment Proposals on QCD Physics Volume 3A: CBM ~ 450 pages Volume 3B: PANDA, PAX, ASSIA~ 600 pages Volume 4: Technical Experiment Proposals on Nuclear Structure and Astrophysics (NUSTAR) ~ 700 pages Volume 5: Technical Experiment Proposals on Atomic Physics, Plasma Physics and Applied Physics (APPA) ~ 500 pages Volume 6: Technical Report Civil Constructions a. Supplies b. Electrical Systems c. Civil Engineering d. Radiation Safety Supplement 1: Cost, Schedule, Manpower Supplement 2: Costbook (5000 entries: 3500 WPs)

  3. Rare-Isotope Production Target Antiproton Production Target FAIR - Facility for Antiproton and Ion Research GSI today Future facility SIS 100/300 UNILAC SIS 18 ESR Super FRS HESR RESR CR FLAIR 100 m NESR

  4. FAIR - Facility for Antiproton and Ion Research Parallel Operations:

  5. FAIR - Facility for Antiproton and Ion Research

  6. FAIR Baseline Cost Costbook TAC Cap (-10%) (M€) (M€) ---------------------------------------------------------------- Accelerators 591 533 Baseline Experiments 200 180 Buildings & Supply Systems 322 289 ---------------------------------------------------------------------------------------------------------- Total Investments 1113 1002 Manpower (2400 MY) 185 185 ---------------------------------------------------------------------------------------------------------- Total Project Construction Cost 1298 1187 Cost increases (beyond inflation) since Conceptual Design Report (CDR-2001): Added Features: 12% True Cost Increases: 11% Spending profile: 2007 – 2017 (construction phase: 2007 – 2014)

  7. FAIR Operation Cost • Cost for: • Accelerator staff (320 FTE per year) • Direct cost for accelerators (6500 hrs/yr) • Experimental equipment • Maintenance of buildings • IT • Safety • … • … in the process of being worked out! ~ 120 M€ per year - approx. 10% uncertainty - full price tag from 2015 on - in 2005 prices

  8. FAIR-GmbH Management FAIR Line Management GSI Line Management Laboratory Facility & Site Operations Engineering Design Site Preparation and ES&H Technical & Civil Construction Production Supervision Assembly & Commissioning Strategic Planning Budget & Financing Controlling Scientific Program & Schedule International Employment GSI-mbH Management FAIR (Facility) Construction / Operation (Long-term) Contractual Arrangements "Geschäftsbesorgungsvertrag" Site Lab.-Services Landlord Activ. POF-Research Res.-Infrastr. Scientific- Technical Infrastructure Administrative Infrastructure

  9. Issues – Questions – Next Steps: • Acceptance of Baseline Technical Report by ISC (by May 2006) • in particular: cost – schedule – manpower • BMBF: accepted with conditions (s. next point) • Financing: • guidelines from FCI working group • BMBF: German federal project budget fixed • other sources: 50 M€ from 25% scaling from partners • GSI comitted to carry all manpower cost (re-directed effort) • remainder? • Government-level negotiations • letters from German Minister (Schavan) to foreign ministries • with requests to identify counter-partners for negotiations • and to begin negotiations • Finalize Baseline Technical Report (by June 2006) • Finalize legal documents and organizational structure • (2-company model) etc. (by Fall 2006)