Alpine Aqueduct Cathodic Protection System Project - Phase 2

Alpine Aqueduct Cathodic Protection System Project - Phase 2. October 23, 2013 Bid Summary. Electrically Discontinuous Sections. Jordan Aqueduct-Reach 4 / Alpine Aqueduct – Reach 3 Cathodic Protection System Project Electrically discontinuous sections of AA-3 need to be repaired

kuper
Download Presentation

Alpine Aqueduct Cathodic Protection System Project - Phase 2

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Alpine Aqueduct Cathodic Protection System Project - Phase 2 October 23, 2013 Bid Summary

  2. Electrically Discontinuous Sections • Jordan Aqueduct-Reach 4 / Alpine Aqueduct – Reach 3 Cathodic Protection System Project • Electrically discontinuous sections of AA-3 need to be repaired • Install Deep Well Anode Beds and apply induced current

  3. General Work Sequence • External Bonding • Limited Surface Disturbance Excavation Methods • Divide and Locate Method for repairs • Discontinuous Section 688+85 to 697+97 • Discontinuous Section 681+72 to 699+54 • Excavation sites to be restored to pre-construction condition by end of contract (May 1, 2014)

  4. General Work Sequence • Internal Bonding • AA-3 drained and access points opened by District O&M staff • SAFETY – Confined Space • Remove mortar lining, clean steel, install bonding straps, protective coating epoxy, replace mortar lining, and cleanup of construction debris • Continuity testing by CCT • District staff will close all access points • All work completed by April 1, 2014

  5. Bid Summary

  6. QUESTIONS