1 / 10

MVD System Modernization Implementation Request

MVD System Modernization Implementation Request. May 21, 2014. Agenda. Project Purpose Business Objectives Technical Objectives Budget Schedule Scope Incorporating Lessons Learned Questions. Purpose.

lindley
Download Presentation

MVD System Modernization Implementation Request

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MVD System Modernization Implementation Request May 21, 2014

  2. Agenda • Project Purpose • Business Objectives • Technical Objectives • Budget • Schedule • Scope • Incorporating Lessons Learned • Questions

  3. Purpose • Replace the existing, fragile MVD system for Driver and Vehicle transactions, while meeting all 752 of the requirements of RFP #30-333-12-12463.

  4. Request 05/21/2014 • Certify the remaining funds appropriated for the project.

  5. Current Status • Project Kickoff held March 5, 2014. • All hardware and software has been ordered. • Development environment is in place. • IV&V Contract has provided the IV&V project plan and the Initial Review. • Definition Task for Release #1, Driver Services started March 20, 2014. • Base COTS Driver has been installed in Development environment. • Core Tapestry team members have been provided with training and access to Tapestry Development, and the Fast FCR toolset.

  6. Budget – Implementation Phase • Includes: • Additional eight (8) months total in implementation time from pre-contract Delivery dates. • Additional MVD and ITD resources for the additional project schedule to September 5, 2016. • Level 3 support from COTS vendor. • Increased # of workforce shift personnel for both ITD and MVD.

  7. Schedule

  8. Scope • All mandatory requirements from RFP# 30-333-00-12463 • All optional requirements from RFP# 30-333-00-12463 to which Fast responded ‘Fully met’.

  9. Accomplished to date • All Fast and TRD staff in place • Co-located facility will be available mid-June • Planning complete • IV&V vendor has submitted the plan and the initial review • FastDS-VS licenses purchased and installed in the development environment • All hardware and software for four (4) environments purchased. • Definition Task started 3/20/2014. This will complete September 2014.* Definition consists of reviewing the RFP Requirements, deciding how the requirements Will be met by the Tapestry system, and how the New Mexico MVD business rules will be incorporated into the COTS package.

  10. Questions

More Related