140 likes | 348 Views
Civil Works. Baltimore District River and Harbor Projects. PROJECT: Baltimore Harbor & Channels, VA - Cape Henry & York Spit Channels TYPE WORK: Maintenance DEPTH: 50 Feet WIDTH: 1,000 and 800 Feet LENGTH: 3 and 18 Miles QUANTITY: 100,000 cy TYPE OF MATERIAL: Sand
E N D
Civil Works Baltimore District River and HarborProjects
PROJECT: Baltimore Harbor & Channels, VA - Cape Henry & York Spit Channels TYPE WORK: Maintenance DEPTH: 50 Feet WIDTH: 1,000 and 800 Feet LENGTH: 3 and 18 Miles QUANTITY: 100,000 cy TYPE OF MATERIAL: Sand PLACEMENT AREAS: Dam Neck Ocean and Wolf Trap Alternate DIST. TO PLACE. AREA: 7 Mi TYPE OF EQUIPMENT: Hopper SMALL BUSINESS SET ASIDE: No LAST DREDGED: 2006/2004 ENVIRONMENTAL WINDOW: Dec 1 – Mar 31 REASON FOR WINDOW: Sea Turtles COMMENT: McFarland completing work delayed from summer due to turtle take limit.
FY07 FY08 FY09 SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT Scheduled FY08 Dredging Work in Baltimore District Hopper Dredge McFarland Baltimore Harbor & Channels, VA - Cape Henry/York Spit Sea Turtles 100 KCY Sea Turtles - Screens and Observers Page 1 of 1
PROJECT: Wicomico River, MD TYPE WORK: Dike Construction DEPTH: 14 Ft. WIDTH: 150 Ft. LENGTH: 10 miles. PLACEMENT AREA: Upland SMALL BUSINESS SET ASIDE: Yes LAST DREDGED: 2007 ENVIRONMENTAL WINDOW: June 16 – February 14 REASON FOR WINDOW: Anadromous fish spawning PRESIDENT’S BUDGET: $800,000 ADVERTISING DATE: Apr 2008 BID OPENING DATE: May 2008 AWARD DATE: June 2008
FY07 FY08 FY07 SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT Scheduled FY08 Dredging Work in Baltimore District Hydraulic Pipeline Dredge Maintenance Dredging Wicomico River, MD Anadromous Fish DIKE CONST Poplar Island, MD CELL 6 DEWATER Page 1 of 1
PROJECT: Baltimore Harbor & Channels, MD TYPE WORK: Maintenance DEPTH: 50 Feet WIDTH: 400 - 800 Feet LENGTH: 10 – 15 Miles QUANTITY: 2,000,000 cy TYPE OF MATERIAL: Silt and clay PLACEMENT AREAS: Poplar Island and Hart-Miller Island DIST. TO PLACE. AREA: 20 -30 Miles TYPE OF EQUIPMENT: Clamshell SMALL BUSINESS SET ASIDE: No LAST DREDGED: 2000 - 2007 ENVIRONMENTAL WINDOW: Dec 1 – July 31, Sep 1 – Mar 31 REASON FOR WINDOW: Dredged Material Drying PRESIDENT’S BUDGET: $16,655,000 ADVERTISING DATE: Aug 2007 BID OPENING DATE: Oct 2007 AWARD DATE: Nov 2007
FY07 FY08 FY09 SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT Scheduled FY08 Dredging Work in Baltimore District Mechanical Dredge Maintenance Dredging Baltimore Harbor & Channels 2.0 MCY Drying at Poplar Island Drying at Poplar & Hart-Miller Page 1 of 1
Existing Dredged Material Placement Sites
FY08 FY09 FY10 FY11 FY12 Scheduled FY08-12 Dredging Work in Baltimore District PROJECT Baltimore Harbor & Channels 2.0 MCY 2.0 MCY 2.0 MCY 2.0 MCY 2.0 MCY Poplar Island EXPANSION Wicomico River 100 CYS 100 CYS Page 1 of 1