K. Long, 16Nov2009. Target:. Schedule for T2 re-instatement:. T2#2: Next steps: Non-DLC bearings: Delay in material delivery: Torlon delivery expected this week Vespel (preferred material) expected 12 December In parallel:
E N D
K. Long, 16Nov2009 Target:
Schedule for T2 re-instatement: • T2#2: • Next steps: • Non-DLC bearings: • Delay in material delivery: • Torlon delivery expected this week • Vespel (preferred material) expected 12 December • In parallel: • Checking forces generated with mis-aligned coils using OPERA model (PS, TB): ongoing • Devising magnetic QA rig (GB + Shf): ongoing • Devising concept for winding coils that is more precise • Will be discussed at Trgt w/s 02Dec09 in Sheffield • Schedule T3: • Machining of parts progressing well • Coils for T3 prepared in Sheffield: • Will consider whether to use new coils or present coils based on:magnetic analysis; Magnetic QA on T2 stator
T3 schedule: • T3 schedule still looks OK: • Need to expedite ‘R&D’ work on T2#3 • Which is in hand