An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Module 16Case Studies in Performance-Period Administration Enforcing ECM Performance Requirements — Healthcare Facility

  2. Example • Site: Health-Care facility • Primary Care Clinic • Pediatric Clinic • Internal Medicine Clinic • Surgical Clinic • Physical Therapy • Optometry Clinic • Occupational Medicine Clinic • Public Health and Education Center with pathology, radiology, and pharmacy services • Dental Clinic

  3. Project Economics • $1,326,000 Implementation Price • $260,000 Pre-Performance-Period Payment • $186,000 Finance Procurement Price • $1,252,000 Total Amount Financed • $188,300 Estimated First-Year Savings • $170,100 Annual Savings Guaranteed • $95,000 Construction-Period Savings (paid with first-year payment) • 17-year term

  4. ESPC Scope of Work • HVAC Modifications • Chiller and Cooling Tower Replacement • HVAC Controls • Energy Management Control System • Lighting Upgrades • T12 to T8 Relamping • Submetering • Install water meter so building can be changed from billing /SF to metered billing • Natural Gas and Electric Meter Existing

  5. Economics

  6. M&V Approach • Chiller and Cooling Tower Replacement • Option C • Energy Management Control System • Option C • Lighting Retrofit • Option C • Submetering • Option A

  7. First-Year M&V Report

  8. A Closer Look

  9. Problem • DDC control system night setback not able to return areas to normal operating conditions. • Agency overrides night setback to continuous operation. • Higher than predicted run hours. • ESCO takes $15,500 annual credit for override.

  10. Resolution • Recommissioning of the system • Re-evaluation of thermostat location • Recalibration of thermostat and sensors • Verify setpoint temperatures • Review sequence of operations • Verify AHU discharge temp controls operating • Check outside air sensor operation • Install humidity sensor in occupied space • ESCO responsible to return areas to conditions established in DO RFP by the start of next occupied period.

  11. Lessons Learned • Sound M&V plan provides basis for evaluation • Government review of annual report identifies shortfall • Detailed DO RFP provides sound backup to M&V plan • Working together can provide workable solution