Transmission Service Requests Overview 2008 Transmission Summit July 29, 2008 New Orleans, LA
ICT TSR Responsibilities • Maintain, Administer, and Post for Long-Term Transmission Service Requests • Long-term service requests (≥1 year) or requests outside the Study Horizon (18 months) • Schedule, send, receive, and validate all Study Agreements • System Impact Study Agreement (SISA) • Facilities Study Agreement (FSA) • Affected System Agreements • Respond to any inquiries by the Transmission Service Customer via phone, email, and IssueTrak.
ICT TSR Responsibilities • Perform System Impact Study • Post all study reports (SISR & FSR) and documentation as per Entergy’s Tariff • Provide all notices to the customer as required
ICT TSR Responsibilities • Review and validate the results of the Facilities Study • Classify upgrades as Base Plan or Supplemental as per Attachment T of Entergy’s Tariff • Coordinate studies with any Affected Systems
Entergy TSR Responsibilities • Review System Impact Study Report (SISR) • Tender, enter into, and file all Transmission Service Agreements • Enter into 3rd party Facilities Study Agreement (FSA) with ICT and Customer • Perform Facilities Study
Transmission Service Requests (Since 2007 Summit) • ICT has sent out 248 SISAs • ICT has performed and posted 154 SISRs on time • ICT has 17 SIS in process • Entergy has performed 48 FSRs on time • Entergy has 5 FS in process
System Impact Studies • ICT has performed and posted 154 SISRs • 53 Point to Point Requests • 9 Monthly Requests • 101 Network Requests • 4 Monthly Requests • 3 Affected System Requests • ICT has 17 SIS in process • 2 Monthly Firm PTP • 1 Monthly Network • 6 Long Term Firm PTP • 3 Long Term Network • 5 Affected System
Facilities Studies • Entergy has performed 48 FSRs • 14 Point to Point Requests • 13 Long Term Firm Requests • 1 Affected System Request • 34 Network Requests • 31 Yearly Network Requests • 3 Affected System Requests • Entergy has 5 FS in progress • 5 Yearly Network Requests
Questions / Commentsspp.issuetrak.comQuick Pick: ICT Planning– Transmission James Lyle501-614-3561JLyle@SPP.org English Cook501-614-3555ECook@SPP.org