Central Chilled Water Facility – Phase II

Central Chilled Water Facility – Phase II. Alan Raphael MPO Project Manager CFAC Committee Review October 5, 2010. Technical Progress. Chilled Water Plant Expansion General Contractor – E. W. Howell $15.3M Contract shared with BNL & NSLS-II (~55/45 split)

mostyn
Download Presentation

Central Chilled Water Facility – Phase II

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Central Chilled Water Facility – Phase II Alan Raphael MPO Project Manager CFAC Committee Review October 5, 2010

  2. Technical Progress • Chilled Water Plant Expansion • General Contractor – E. W. Howell • $15.3M Contract shared with BNL & NSLS-II (~55/45 split) • Managed by BNL F&O, Giffels Engineers is A/E • Contract 90% complete • Buildings enclosed • All equipment delivered and set • Testing in progress • Entering startup phase • Transition to Operations Plan in place • Detailed systems checklists developed for equipment and systems “readiness evaluations” • Contract completion February 2011 • ~ 3 – 4 months float from NSLS-II critical path

  3. Central Chilled Water Facility – Phase II Preparation Basement Mat(10/22/09) Shoring 600 (9/25/09)

  4. Central Chilled Water Facility – Phase II Structural Steel Frame (12/31/09) Pipes in Basement (12/04/09)

  5. Central Chilled Water Facility – Phase II Metal Deck Pour on1st and 2nd Floors (03/02/10) Cooling Tower Concrete (01/22/10)

  6. Central Chilled Water Facility – Phase II Cooling Towers (04/09/10) New Liner Panel (03/19/10)

  7. Central Chilled Water Facility – Phase II 42” Cooling Tower Water Supply 30” and 14” Cooling TowerWater Return Piping(06/04/10) Roofing Material Arrived On-Site (05/07/10)

  8. Central Chilled Water Facility – Phase II MCC’s Rigged into the Electrical Mezzanine Level(07/16/10) VFD’s Rigged into the Electrical Mezzanine Level(07/16/10)

  9. Central Chilled Water Facility – Phase II Switchgear for Substation 600-B Delivered and Rigged into Place(08/06/10) Transformers for Substation 600-B Delivered and Rigged into Place(08/06/10)

  10. Central Chilled Water Facility – Phase II Buss Ways Installed at Electrical Mezzanine Level (09/03/10) Cables Pulled to Transformers at Sub 600-2 (08/27/10)

  11. Work in Progress • Performing electrical equipment checkouts • Finalizing mechanical startup plans • Equipment/system readiness evaluations in process • No significant change orders to date • Safety performance has been good • Contractor proceeding on schedule

  12. Look Ahead • Electrical systems startup in October • Condenser water system startup in November • Chilled water system startup in December • BORE to be performed incrementally: • Outdoor substation • Pumphouse (Bldg. 600A) • Cooling Tower and Treatment Building • Building 600