PR90006, Commercial Systems Information Lifecycle Management (ILM)

PR90006, Commercial Systems Information Lifecycle Management (ILM). Hope Parrish, ERCOT. Background on project Review of related protocol Market Impact Seek RMS Endorsement. ILM Project 90006 Background. Approved Project Goals

orea
Download Presentation

PR90006, Commercial Systems Information Lifecycle Management (ILM)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PR90006, Commercial Systems Information Lifecycle Management (ILM) Hope Parrish, ERCOT RMS

  2. Background on project • Review of related protocol • Market Impact • Seek RMS Endorsement RMS

  3. ILM Project 90006 Background • Approved Project Goals • ERCOT needs to ensure that data and information are stored in an efficient manner based on Protocols and the business process needs while making best use of storage capacity and system utilization. • To define and implement an ERCOT Enterprise Information Lifecycle Management (ILM) Strategy based on ERCOT’s current and future technological state. • Project Benefits • Maintain ability to support future ERCOT and Market efforts • By controlling the amount of data and storage consumed in source and archiving systems • Performance optimization • By removing extra copies of data • Implement an Enterprise ILM strategy for required source systems • Allows ERCOT to better maintain SLA’s • Implement an Enterprise ILM strategy for Archive Systems (ISM) • Allows ERCOT to maintain compliance and enforce data retention policies • Storage optimization by releasing/reallocation of storage efficiently • Significantly reduces data center cost and future project risks • Changes to business processes to align with minimum amount of data required to meet Protocols and data retention policies RMS

  4. ILM Project 90006 Background • Project will be worked in phases by database and include an evaluation of Commercial Systems source system and archive system databases • Middleware – used for retail transaction processing • Current project focus • Registration – used for ESIID and Market Participant registration and disputes • Settlements & Billing – used for data aggregation, load profiling and settlements • ISM – archive system • Project will also create and modify ERCOT internal policies in support of data retention and ILM strategies RMS

  5. Protocol Req’ts for Transaction Reprocessing and Data Retention • ERCOT will be exercising the following Protocol Requirements as part of the ILM project: • Protocol Section 15. Customer Registration • 15. Customer Registration “ERCOT will reject any initiating transaction due to date reasonableness if the requested implementation date is of more than ninety (90) days in the future or two hundred seventy (270) days in the past.” • Protocol Section 17. Market Data Collection and Use • 17.2.5 Data Retention “The data stored in the Data Warehouse and Data Archive shall be available online for four (4) years from ERCOT’s creation or receipt of the data. Data passed to the Data Archive will be stored by ERCOT for a total of seven (7) years.” • Nodal Protocol Section 17. Market Monitoring and Data Collection < note: effective with Nodal go-live> • 17.2.5 Data Retention “Data stored in the Data Warehouse and Data Archive must be available online for four (4) years from ERCOT’s creation or receipt of the data. Data stored in the Data Archive must be maintained by ERCOT for a total of seven years from ERCOT’s creation or receipt of the data.” RMS

  6. Market Impact • Currently when executing Find Transaction through TML all transaction history is returned based on the dates provided in the FROM/THROUGH selection. • With PR 900006 implementation: • By default, the service will return 270 days of transaction data history at the same response time rate as today or better. • An indicator will be available on Find Transaction as a control to request 4 years of data • The control will allow for the return of 4 years of transaction data to be available with a potential for slower response time RMS

  7. Find Transaction RMS

  8. RMS Endorsement ERCOT is seeking endorsement for the following items: • ERCOT will provide market participants with the ability to request FIND Transaction data for up to 4 years As a result, the Market should realize the following benefit: • Maintained or improved performance in transaction processing • ERCOT meets expectations set in current Protocols Information will still be available via Siebel Service Order Extract: • Siebel Service Order Extract may be scheduled by CRs and TDSPs to receive the following: • Quarterly – 4 years of Service Order data • Monthly – 365 days of Service Order data • Daily – previous day’s Service Order data additions and changes • Siebel Service Order Extract User Guide may be found in the Retail Section of http://www.ercot.com/services/mdt/userguides/index. The DDL is posted on TML Public Data Definitions folder. RMS

  9. Questions? RMS