230 likes | 334 Views
ATDD Southwest Experience. And Other Important Info. Location, Location, Location. What is the Exact location of the site Moab UT Surveyed site moved by host to parking lot Grants NM On lava flow and digging an issue Clovis NM
E N D
ATDD Southwest Experience And Other Important Info
Location, Location, Location • What is the Exact location of the site • Moab UT • Surveyed site moved by host to parking lot • Grants NM • On lava flow and digging an issue • Clovis NM • Surveyed site near walking trail and host was concerned about vandalism
Reasons for a Concrete Truck • Hand Mixing takes a long time • 280 forty pound bags of Redi-Mix needed (11,200 pounds) • 280 Gallons of water needed (2,352 pounds) • A total weight of materials needed 5.6 Tons
Reasons For a Site Host • Care for Site vegetation • Empty the Gauge • Perform Minor Unscheduled Maintenance • Recover Data
What Happens During an Install? • USRCRN sites normally take Two Days • Day One is Site Infrastructure • Day Two is Hardware and Cal’s