An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Network Rail & Northern Rail Co-ordination Meeting FHR6 Blockade Works 12th August 2013 1

  2. Todmorden Curve Aerial View of Todmorden Curve 2

  3. Todmorden Curve The project involves: • Reinstatement of approx 300m of new track formation, ballast, sleepers and rail • 1nr new turnout from the Dn MVN2 and 1nr new crossover on the MVN2 line between Todmorden viaduct and Todmorden Station • Heavy maintenance of existing turnout and crossover on the FHR6 line • New signalling, telecoms and power equipment on and off the new chord and spacing alterations between Dobroyd and Summit Tunnel (late new scope) • Control modifications to Preston Powered Signal Box • Footbridge at Dobroyd Crossing (by National Footbridge Team)

  4. Todmorden Curve Setting Up Site

  5. Todmorden Curve Route of New Chord - Now Cleared of Trees

  6. Todmorden Curve Key Milestones • Contract Award (Buckinghams MAFA) Jul-13 • Mobilise to site Aug-13 • Installation of new S&C Nov-13 (disruptive access wk 31 and 32) • Heavy Maintenance (FHR6) Dec-13 (during Holme Tunnel disruptive access) • Commission Signals MVN2 Jan-14 (disruptive access wk 41 24hr) • Commission and Hand back Chord Feb-14 (disruptive access wk 45 50hr) Current Status • Site setup under way • Material deliveries over next 8 weeks – engineering train • Design underway • Survey and GI works in progress 6

  7. Holme Tunnel Repair 7

  8. Holme Tunnel Repair Background • ELR: FHR6 Gannow Junction to Hall Royd Junction • Masonry & brick tunnel • Constructed between 1845 and 1849 • 265 yards (242 metres) long • Located near the village of Holme Chapel, Cliviger 8

  9. Holme Tunnel Repair Defects • Severe distortion of tunnel bore at Todmorden end • Distortion of Todmorden portal • Brickwork defects along tunnel length Causes • Landslide movements • Seismic activity and faulting • Climate and rainfall • Streams and groundwater • Mining at Todmorden End • Excavations at landslide toe 9

  10. Holme Tunnel Repair Solution • Undertake primary and secondary grouting prior to main works • Remove and replace signalling and tellecoms cables • Remove and replace 600m of Permanent Way • Replace existing masonry lining at Todmorden end with new concrete lining and strengthen invert. • Reconstruct Todmorden Portal • Repairs at Burnley end to brickwork lining • Install new 6ft drainage Remit • Reinstate structural integrity to allow return to normal asset management regime • Reinstate Standard Gauge Clearance • Removal of performance and line closure risk due to continued deterioration • Allow removal of 20mph PSR, and passive provision for 75mph line speed 10

  11. Holme Tunnel Repair Solution • Undertake primary and secondary grouting prior to main works • Remove and replace signalling and tellecoms cables • Remove and replace 600m of Permanent Way • Replace existing masonry lining at Todmorden end with reinforced concrete lining and strengthen invert. • Reconstruct Todmorden Portal • Repairs at Burnley end to brickwork lining • Install new 6ft drainage Remit • Reinstate structural integrity to allow return to normal asset management regime • Reinstate Standard Gauge Clearance • Removal of performance and line closure risk due to continued deterioration • Allow removal of 20mph PSR, and passive provision for 75mph line speed 11

  12. Holme Tunnel Repair Key Milestones • Establish Site Compound Jul 2013 • Start preliminary grouting Jul 2013 • Finish preliminary grouting Nov 2013 • Blockade Start Date 9th Nov 13 • Remove S&T cables 11th Nov 13 • Remove existing p-way 12th Nov 13 • Establish work area in tunnel 13th Nov 13 • Start tunnel relining works 13th Nov 13 • Start portal works 11th Dec 13 • Complete relining works 2nd Mar 14 • Complete portal works 13th Mar 14 • Re-establish S&T cables 13th Mar 14 • Grade ballast and lay track 19th Mar 14 • Test and commission 24th Mar 14 • Blockade end date 24th Mar 14 • Demobilise site 11th April 14 Progress to Date • Site compound established • Installation of Road Rail Access Point • Drilling and grouting in progress • Progressing finalisation of design 12

  13. Holme Tunnel Repair 13

  14. Holme Tunnel Repair 14

  15. Holme Tunnel Repair 15

  16. Holme Tunnel Repair 16

  17. Additional Work Items • Structural Repairs at Lydgate Viaduct 17

  18. Additional Work Items • Structural Repairs at Lydgate Viaduct • Embankment stabilisation at Kitson Wood • Embankment stabilisation at Walk Mill 18

  19. Additional Work Items • Structural Repairs at Lydgate Viaduct • Embankment stabilisation at Kitson Wood • Embankment stabilisation at Walk Mill • Improved drainage, waterproofing and structural repairs at Burnley Road Bridge 19

  20. Additional Work Items • Structural Repairs at Lydgate Viaduct • Embankment stabilisation at Kitson Wood • Embankment stabilisation at Walk Mill • Improved drainage, waterproofing and structural repairs at Burnley Road Bridge • Minor works to 27 structures along the route 20

  21. FHR6 Blockade Works 12th August 2013 Network Rail & Northern Rail Co-ordination Meeting 21