150 likes | 327 Views
NuMI Beam line Power Supplies. The supplies in the line is detailed Main Ring Style…………………..…1 PEI/Transrex 500Kw……………….10 PEI 20Kw…………………………..10 PEI 240Kw…………………………..2 MI Correction elements……..……….6. Transrex vs PEI 500Kw supplies. Rework.
E N D
NuMI Beam line Power Supplies • The supplies in the line is detailed • Main Ring Style…………………..…1 • PEI/Transrex 500Kw……………….10 • PEI 20Kw…………………………..10 • PEI 240Kw…………………………..2 • MI Correction elements……..……….6 Steven Hays E/E Support
Transrex vs PEI 500Kw supplies Steven Hays E/E Support
Rework • All of the PEI style power supplies have been modified and installed • Controls cables are installed in MI60 and MI62 but final connection will completed after the data base is setup. Steven Hays E/E Support
Series Regulation • The groups of supplies will be regulated by one current regulator. • Each supply will have an SCR Unit with a closed voltage loop, the same as the single supplies. • All the supplies act as if they are one. • The supplies will all receive the same voltage reference. • The P1 and A1 lines have this supply configuration in operations now. Steven Hays E/E Support
Upgrades • Reused “Main Ring SCR Unit”. • Better Voltage control. • Maintenance techs have experience and knowledge. • Little or no down time due to these chassis. • Need new current loop added to the chassis. • Added a filtered voltage monitoring card to the chassis. • New Gate Firing circuits. • Two Quadrant operation. (Invert). • Remove Diodes in the Bypass and add SCRs. Steven Hays E/E Support
Ramp Calculator • Each Load Will Use the Max P.S. Voltage. • Operation will have only one data point to adjust. • Same control as the P1,P2,P3 and A1 lines Steven Hays E/E Support
Power Supply Controls • C468 Ramp Generators: Current Reference. • Each magnet load will have one current reference. • Voltage reference feed forward created by P.S. reg. • L di/dt +IR and Integrator Steven Hays E/E Support
MI Regulation Improvements • The C468 card’s DAC output has too much noise and drift. • We are installing a local DAC in the current regulation system to improve the noise. • The local DAC has better temperature drift numbers but is not in a better environment. • Additional improvement will be installed as needed. • Temperature regulation of the DAC. • Flattop correction for magnet temperature. (JITTER) • Low Beta/MI style Current regulator. • BmLB Learning system. Steven Hays E/E Support
Series Power Supply Controls • The reuse of existing equipment requires a series connection of two or three supplies on each of three magnet loops. • The operations interface needs to be simple. • Look like only one supply to the operations crews. • Controlled turn on and off. • Access for maintenance needs to be simple. Steven Hays E/E Support
Beam Loss Issues • The current regulation system has an absolute value circuit on the current error and will abort the beam in the MI if the supply is out of regulation. • For the more critical loads an independent window detector will not allow the beam to leave the MI if the current is not within the window at flattop time. • Two of the supplies have critical device controllers installed. Steven Hays E/E Support
Present Status • All the PEI supplies are installed. • Five are installed at MI-60. • The HV101 loop has 3 supplies in series. • The Lam60 and V100 loops are single supplies. We expect to add filters later for improved regulation. • A Main Ring style supply is being installed at MI-62 for the V105 loop. • A single PEI is installed at MI-62 for the V110 loop. A filter will also be added to this loop. • All the 20Kw quad loop power supplies are installed. Steven Hays E/E Support
Present Status Continued. • The smaller 20Kw supplies have had simple modifications and installed in MI-60 and MI-62. • The digital status has been increased. This will read back to the MCR all things that trip the supply. • The MI ring uses this type of supply in the MI-8 line and the supplies being installed in the NuMI line will be brought up to the same level of controls. Steven Hays E/E Support
Pulsed Power Source • The MI-62 power panel and transformer has enough unused equipment for all the NuMI supplies being added as a result of the addition of the Main Ring supply for the V105 loop. • MI-60 has a new power panel installed but the 1,500Kva pulsed duty transformer has not been installed. • All the line power and controls installations have been completed at both 60 and 62 with with the exception of the V105 supply. Civil construction needs to be completed before the transformer can be installed. • All load connections will require extended MI access. Steven Hays E/E Support
Expected Completion of Supplies • The supplies in the MI-62 and MI-60 building should be completed Sept 2000. Assembly of the Main Ring supply cabinet has started but will not be able to be tested until the civil construction is complete. • All the controls can/will be tested. We have started the HV101 power supply controls testing. • The Voltage regulation system can be tested using a temporary load. The current regulation and filter testing will have to wait until the loads are connected. Steven Hays E/E Support
NuMI Regulation Improvements • Any improvements to the MI beamline regulation system will be added to the NuMI line supplies. • The improved flattop regulation will be added after we have proven it in the MI lines. • Improved current feedback in terms of DCCTs will be added as needed for each loop. • The Low Beta/MI ring current regulation chassis will be added for even better current reference as needed. • The BmLB regulation system will be used only if necessary. Steven Hays E/E Support