110 likes | 123 Views
This document provides design parameters and key assumptions for dump load calculations at PS2, covering operation periods, proton amounts, and injection/extraction functionalities. It includes detailed beam load summaries and factors influencing H-Injection processes.
E N D
Beam load estimates for the PS2 Beam Dump Systems T. Kramer, M. Benedikt, B. Goddard
Main PS2 design parameters and key assumptions for the dump load calculations • Assumed 200 days of operation • Maximum of 1.08 x 1021 protons /y • All calculations are done in a rather conservative way T. Kramer AB-BT-TL
Dump functionalities • Injection line setting up • Fast injection setting up • H- Injection • Emergency abort • Machine development • Machine setting up • Extraction line setting up • Slow extraction ‘remaining beam’ T. Kramer AB-BT-TL
H- Injection • 6.4x1019 p.a. (5.92%) @ 4 GeV details later…. • Emergency beam abort • assumed 0.5% of cycles dumped • 5.4x1018 (0.5%) particles p.a. (50% @ 4-20 GeV) • Machine setting up • 6 days (2 per beam); 20% of full intensity • 6.5x1018 p.a. (0.6%) (50% @ 4-20GeV) • Machine development • 100h p.a. 20% of full intensity • 4.3x1018 p.a. (0.4%) (50% @ 4-20 GeV) • Particles remaining after slow extraction • Max. 1 % remaining particles; 50 GeV; operational 50% p.a.; 3.6s cycle • 3.6x1018 p.a. (0.33%) • Fast injection setting up and failures • 1 day p.a.; 20% dumped; 100 failures p.a. • 1.08x1018 p.a. (0.1%) @ 4 GeV • Setting up of injection transfer line • 4 days p.a.; 10% intensity; 20 foil exchange interventions; • 3.06x1018 p.a. (0.28%) @ 4 GeV • Setting up of extraction transfer line • 2 days p.a.; 30% intensity; • 3.25x1018 p.a. (0.3%) @ 50 GeV T. Kramer AB-BT-TL
Summary of beam loads Table 1: Beam loads @ “high Energy” Table 2: Beam loads @ “low Energy” T. Kramer AB-BT-TL
Schematic overview PS2 injection transfer line dump TED(s) PS2 extraction line dump TED SPS External H- injection dump ? ? TT12 TT10 from SPL EAs Internal fast injection dump External beam line dump PS2 Internal emergency dump T. Kramer AB-BT-TL
H- Injection - Beam Loads • Unstripped beam • 2 kW unstripped H-,H0 (5% efficiency) • 5.4x1019 p.a. (5%) • Yearly startup • 8x1018 p.a. (0.75%) • Setting up • Injection systems / foil exchange • 1.8x1018 p.a. (0.16%) T. Kramer AB-BT-TL
H- Injection - extract beam back to TT10 Overview of PS2 H-Injection; B. Goddard; PS2 meeting; 05/2007 T. Kramer AB-BT-TL
H- Injection - Factors of Influence Foil material • Stripping efficiency • Emittance dilution • Foil heating To be considered: • Lorentz Stripping • H0 excited states Foil thickness Temperature Stripping efficiency Beam blow up 5% Lifetime <0,1 pi mm mrad Losses! Beam load H0/H- Some optimization should be possible - studies Size, activation, position of the beam dump T. Kramer AB-BT-TL
Internal emergency dump • Advantages • System is easier to build, cheaper, desirable from point of operations, “some internal dump” to set up the extraction is anyway needed • Disadvantage • For operations like in the SPS a very high beam load is expected - Radiation source within the machine • Possible solution (as proposed): • Internal dump only takes the beam which really has to go there (8x1018 4-20 GeV + 2.7x1018 p@50 GeV p.a.) • Whenever there is time to extract the beam safely a beam line dump is used (slow extraction, machine development. 5.5x1018 @ 20-50 GeV + 6.9x1018 @ 50GeV p.a. ) • External dump at end of beamline in well-shielded EA zone? T. Kramer AB-BT-TL
Summary of loads and issues • Issues • Need for TEDs/beam stoppers at the end of transfer lines…including for ions and p+ from PSB before SPL comes on line. • Configuration for injection and extraction region….becoming congested. • Extraction and dumping of unstripped H- beam (acceptance, losses, …) • Optimization of losses for H- injection? Studies need to be done… • Conservative calculation to keep the highest degree of freedom; If we have serious problems concerning feasibility (costs) we have to define more accurate operations and design parameters and look into detail again. T. Kramer AB-BT-TL