Px Ph1 Upgrade - IT, Perugia, 26 Mar 2012

Px Ph1 Upgrade - IT, Perugia, 26 Mar 2012. Stato attività e procurement a Catania ------------- Task now : HDI prod for a small (~30 modules) current-type prod Task future : HDI prod for entire L3. Px Ph1 Upgrade - IT, Perugia, 26 Mar 2012. OUTLINE

quito
Download Presentation

Px Ph1 Upgrade - IT, Perugia, 26 Mar 2012

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Px Ph1 Upgrade - IT, Perugia, 26 Mar 2012 Stato attività e procurement a Catania ------------- Task now: HDI prod for a small (~30 modules) current-type prod Task future: HDI prod for entire L3

  2. Px Ph1 Upgrade - IT, Perugia, 26 Mar 2012 OUTLINE • Procurement of Components for Test Production • Center Setup • Start of Production Activities

  3. Px Ph1 Upgrade - IT, Perugia, 26 Mar 2012 OUTLINE • Procurement of Components for Test Production • Center Setup • Start of Production Activities

  4. Needed Components 4. Signal cable Power cable 3. Power cable 1. HDI 2. TBM

  5. Status of Procurement: HDIs • Critical item: • Certified good spare HDIs do not exist (or so Roland claims) • New prod by same company (Hightech) not possible due to dismission of their original production line • Therefore HDIs are a precious asset. • We have in Catania now 12 HDIs: • 10 given to me by Roland on 01 Feb 2012, ‘recuperable’ (by cleaning) • 2 from a group of 4 given to me by Wolfram during the June 2011 PSI workshop, certainly faulty • 1 shipped to Bari for setup exercises • 1 given to Anna Peisert for setup exercises • Plan: try to convince Roland to give us ~20 more first week of April

  6. Status of Procurement: TBMs • No problem: got 80 • 1 at the June 2011 PSI workshop • 49 from Simon via GianMario on 30 Nov 2011 • 30 fromWolfram on 01 Feb 2012, comingfrom a wafer ‘found’ at PSI

  7. Status of Procurement: Cables • Should be no problem: • Cutoff stretches < ~30cm are plentyfulatPSI • 5 each already in Catania

  8. Px Ph1 Upgrade - IT, Perugia, 26 Mar 2012 OUTLINE • Procurement of Components for Test Production • Center Setup • Start of Production Activities

  9. Assembly & Bonding: Jigs • Top in FIBRAL (eq. HABA) • Built by a commercial company • Quality control done 22 Mar 2012 • Currently at a firm near Rome for anodization • Bottom in PVC • Still under construction in the INFN-CT workshop • in FIBRAL (eq. HABA) • Contrary to earlier thinking, NOT reduced to 5 places, as # HDIs to process doubled, and verified that it still fits in XYZ stage, sideways. • Built by (another) commercial company • Quality control done 22 Mar 2012 • Currently at a firm for anodization

  10. HDI alignment tool • In FIBRAL • Built in 2 copies • Will give one to Bari, as it is needed also there

  11. HDI- & ‘PVC’-handles • in FIBRAL (eq. HABA) • Feature: notch to fold cable(s) underneath in shipping box • Qty. 40 Built by a commercial company • Quality control done 22 Mar 2012 • Currently at a firm near Rome for anodization • in Plexiglass • Feature: notch to fold cable(s) underneath in shipping box • Qty. 40 still under construction in the INFN=CT workshop

  12. Assembly & Test: XYZ Stage • Started to play with it • Solved question about parallel port no longer available on many PCs. • Found a good PC which has it • Waiting for sw upgrade from company: • Windows vs. DOS

  13. HDI test setup: PSI46 + 6 ancillary boards! • PSI46 • in house • Module Interface • HDI-Testboard Adapter • LED-display push-button control box • Relay board • Should be ready in Taiwan • Delivery expected anytime now • Compensation with TIDs • Spring-loaded probe card to probe HDI • Under constrcttion at KU • ETD: mid April. • Compensation with TIDs • Bridge board • Replace with short stretch of cable and pins to be built in house

  14. Handling & Shipping • Shipping Boxes • Qty 5 builtin the INFN-CT & INFN-LNS workshops in Plexiglas: enough for test prod • 15 more (estimated needed for routine prod) on hold pending investigation of ESD-safe material issue • EDS safety issue raised at last Module Prod mtg. • At PSI they think there is no problem as long as box is handled while earthed • Even Alan Honma estimates covering main external surfaces with conductive film is enough • Working with a specialized company (ELBO Services, Parabiago, MI) for possible • Single-piece Construction from mold • Purchase of conductive-in-volume plastic sheets • Modified-atmosphere ‘Food’ sealer • No fondi INV nel 2012 • In contatto con PG per possibileprestitomacchinadavuoto (soltanto) • Probabilmente OK per test prod • Forsepossibileacquistoimmediato con prestitodaaltrogruppo • Ma dovreiessereabbastanzasicurochefondi INV verrannoassegnatinel 2013 [est. 3 – 3.5 k€]

  15. Consumables - 1 • All ordinary consumables and small tools are arrived: • Glue, dispensers, twizers, swabs, kapton tape, etahnol, etc… • Bonding wire (not expired…) still to be borrowed from Alan • Two specialized consumables: • Specific-size pockets from embossed carrier tape • Custom-size Kapton adhesive tabs

  16. Consumables - 2 3000 (min order) from IBZ.ch ~ 1 kCHF ! 300 from CAEN free! Asked Gianni Di Maio 300 more since CT prod share doubled

  17. Px Ph1 Upgrade - IT, Perugia, 26 Mar 2012 OUTLINE • Procurement of Components for Test Production • Center Setup • Start of Production Activities

  18. Cable-to-HDI Assembly - 1 • First operation in HDI prod is soldering of power cable • Second is assembly of signal cable • These need a jig which we have not built and do not plan to build • It is the most complex and expensive • It is not needed for the upgraded detector (single cable ending with card to be glued similarly to TBM) • Wolfram offered to host Catania people at PSI to do these initial two operations on the few HDIS for test prod using their jig, under the initial supervision/traning of SilvanStreuli: • Arranged for 18-19-20 April 2012 • NunzioGiudice and myself • My plan: About one week before, talk to Roland hoping to convince him to allow us to select, directly at PSI, some ~20 more HDIs

  19. Cable-to-HDI Assembly - 2 • We will take to PSI: • The 12 HDIs we have • The 5 cables we have • The 5 shipping boxes built • The 40 HDI handles built (and hopefully 40 ‘PVC’;-handles) • Some consumables • During this visit we should perform these actions: • Cleaning of the HDIs (Roland said some can be recuperated by cleaning – others are electrically faulty, but we will clean them anyways for bonds to stick) • Chemically treating the power cable so that it can be soldered • Assembling of the 2 cables • Packing the assembled pieced in our boxes, then ESD-safe bags and possibly sealing the bags with their food sealer. [I will also be next to Roland during some managerial EVO meetings towards the TDR]