Loraine Independent School District • Campus Improvements • Construction Update • March 25th, 2013
SCHEDULE STATUS • Block fill in Locker Rooms and Gymnasium is Underway • Steel Erection is Complete • Interior Masonry is Complete Except at Stage and Ramp • Exterior Sheathing is 98% • Exterior Brick Veneer is 70% • Interior and Exterior Framing is 98% except furr downs • Mechanical and Electrical Rough-in is 80% • Roof is 95% Dried-in • Bleachers are Poured • Tie-in to Ag. Building is Framed, Sheathed, and Dried in • HS/ Jr. High Cabinets are finished and ready to install
LOOKING AHEAD • Basketball Goals will be Installed • Windows and Entrances Will Be Completed • Cabinet Finishing and Installation Will Continue • Tape/Bed/Paint Will Continue • Concrete at Stage will be Completed • Steps at Gymnasium Bleachers will be Poured • Concrete will be Poured to Existing Gymnasium • Roofing Sheetmetal will Continue • Sheetrock Installation will Continue