Regional Transmission Planning

Regional Transmission Planning. ISO-NE and TO Responsibilities Per Regional Agreements. The transmission operating agreement (TOA) defines the responsibilities of the RTO and the PTOs

samira
Download Presentation

Regional Transmission Planning

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Regional Transmission Planning

  2. ISO-NE and TO Responsibilities Per Regional Agreements • The transmission operating agreement (TOA) defines the responsibilities of the RTO and the PTOs • The functions to be performed by the ISO and Order 2000 require that the ISO have the requisite operational authority over the PTOs’ transmission facilities • The ISO will be responsible for system planning within the ISO region subject to certain rights and obligations of the PTOs • The PTOs will, among other things, continue to own, physically operate, and maintain their Transmission Facilities and Local Control Centers • Attachment K of the Open Access Transmission Tariff (OATT) describes the regional planning process • The ISO shall conduct the regional system planning process for the PTF in coordination with the transmission-owning entities in, or other entities interconnected to, the New England Transmission System and neighboring systems • The PTOs are responsible for the Local System Planning (“LSP”) process for the Non-PTF in the New England Transmission System. PTF: a Pool Transmission Facility is essentially a networked facility (115 kV and above), with some grandfathered 69 kV facilities Transmission facility: all facilities 69 kV and above, including radials, except as explicitly excluded in the TOA

  3. ISO-NE Planning Process ISO-NE, with VELCO’s help, seeks input from PAC on study scope, needs assessment, solution evaluation ISO-NE, with VELCO’s help, performs studies with participation from other TOs ISO-NE includes study results and describes regional deficiencies in RSP ISO-NE seeks input from PAC on RSP report ISO-NE publishes RSP PAC = Planning Advisory Committee (similar to VSPC but on a regional scale) RSP = Regional System Plan. Used to be RTEP (Regional Transmission Expansion Plan)

  4. Status of Vermont 10-yr Study in ISO-NE Planning Process • ISO-NE will perform the needs assessment analysis from scratch for VT, NH, including parts of MA • The needs assessment study is scheduled to be completed by the end of the year, but will likely be delayed • ISO-NE is finalizing the study scope for the needs assessment • ISO-NE will complete the solutions assessment next year

  5. Overview of Study Scope • Year 2010 ISO-NE load forecast • Summer 90/10 peak reduced from 1183 MW (2008 forecast) to 1100 MW (2010 forecast) • Utilization of demand resources (DR) throughout New England • 89 MW applied homogeneously in Vermont • Supply scenarios • PV-20 flow at 0 MW – NY cannot guarantee support to VT • Highgate at 0 MW – HQ contract is not guaranteed to flow through Highgate • Vermont Yankee re-licensed (ON) or decommissioned (OFF) • Various power transfer conditions • Various contingencies in NY, VT, NH and MA

  6. Treatment of DR in ISO-NE Planning • Demand resources provide capacity benefits up to the value that cleared the ISO-NE forward capacity auctions (FCA) • The capacity is an average hourly value during the performance period over one month • Demand resources in the load flow model include • On peak resources • Real-time demand response • Real-time emergency generation is not included • Only called in the last steps (action #12) of operation procedure 4 (OP4) • Vermont total has been reducing greatly in the last three auctions • New England total amount is limited to 600 MW per market rules • Seasonal peak and critical peak are not included • No such resources in Vermont

  7. Demand Resource Definitions • On peak resources • Non-dispatchable and not weather sensitive load during peak hours • Peak hours are from 1PM to 5PM summer, 5PM to 7PM winter during non-holiday week days • Real-time demand response • Dispatchable load that can respond within 30 minutes and stay off-line for the duration of the event • Measures with no binding air quality permit restrictions during critical peak hours (load level at 95% or greater than the day-ahead 50/50 peak forecast or during shortage hours, i.e. OP4 action 6 or higher)

  8. Demand Resource Modeling • Demand resources are modeled by reducing the load across Vermont, NH and elsewhere • Demand resources are divided by 1.08 to remove the system loss gross-up • Losses are calculated by the load flow program • Demand response is reduced to 75% to represent historical performance

  9. Vermont Forecast Comparisons DR = Demand Resources FCA3 = Forward Capacity Auction #3

  10. Challenges for Vermont Planning Process • Substantial control over VT planning lies at the regional level with ISO-NE • Increasing importance and authority of regional studies that consider interdependencies among states • ISO-NE is not a party to the 7081 MOU • ISO-NE and Vermont planning processes are inconsistent • ISO: annual updates VT: three-year update cycle • ISO: 10-year horizon VT: 20-year horizon • ISO-NE process provides signal to market for DSM and generation alternatives by sharing study results in the regional stakeholder process • Forward capacity market determines what demand-side resources will be used. Cleared demand resources treated as load supply. • Challenge for VT stakeholders: how to keep in-state process relevant and ensure VT goals influence the regional process