1 / 31

Projects: Critical Paths

Projects: Critical Paths. Dr. Ron Lembke Operations Management. PERT & CPM. Network techniques Developed in 1950’s CPM by DuPont for chemical plants PERT by U.S. Navy for Polaris missile Consider precedence relationships & interdependencies Each uses a different estimate of activity times.

sera
Download Presentation

Projects: Critical Paths

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Projects:Critical Paths Dr. Ron Lembke Operations Management

  2. PERT & CPM • Network techniques • Developed in 1950’s • CPM by DuPont for chemical plants • PERT by U.S. Navy for Polaris missile • Consider precedence relationships & interdependencies • Each uses a different estimate of activity times

  3. Questions Answered by PERT & CPM • Completion date? • On schedule? Within budget? • Probability of completing by ...? • Critical activities? • Enough resources available? • How can the project be finished early at the least cost?

  4. PERT & CPM Steps • Identify activities • Determine sequence • Create network • Determine activity times • Find critical path • Earliest & latest start times • Earliest & latest finish times • Slack

  5. 1 2 3 Activity on Node (AoN) Project: Obtain a college degree (B.S.) Receive diploma Attend class, study etc. Enroll 1 month 4? Years 1 day

  6. 1 2 3 4 Activity on Arc (AoA) Project: Obtain a college degree (B.S.) Attend class, study, etc. Receive diploma Enroll 1 month 4,5 ? Years 1 day

  7. 1 2 3 4 AoA Nodes have meaning Project: Obtain a college degree (B.S.) GraduatingSenior Applicant Student Alum

  8. Liberal Arts Sidebar • Alum = ? Alumnus Alumna Alumni Alumnae Alumni

  9. Network Example You’re a project manager for Bechtel. Construct the network. Activity Predecessors A --B A C AD B E BF C G DH E, F

  10. A E C B D G H Z Network Example - AON F

  11. 7 2 9 5 1 3 6 8 Network Example - AOA G D B E A H C F 4

  12. 2 2 3 1 5 3 1 4 4 AOA Diagrams A precedes B and C, B and C precede D B A D C B A C D Add a phantom arc for clarity.

  13. Critical Path Analysis • Provides activity information • Earliest (ES) & latest (LS) start • Earliest (EF) & latest (LF) finish • Slack (S): Allowable delay • Identifies critical path • Longest path in network • Shortest time project can be completed • Any delay on activities delays project • Activities have 0 slack

  14. Critical Path Analysis Example

  15. Network Solution B D E A G 2 6 3 1 1 C F 3 4

  16. Earliest Start & Finish Steps • Begin at starting event & work forward • ES = 0 for starting activities • ES is earliest start • EF = ES + Activity time • EF is earliest finish • ES = Maximum EF of all predecessors for non-starting activities

  17. B D E A G 2 6 3 1 1 C F 3 4 Activity A Earliest Start Solution For starting activities, ES = 0.

  18. B D E A G 2 6 3 1 1 C F 3 4 Earliest Start Solution

  19. Latest Start & Finish Steps • Begin at ending event & work backward • LF = Maximum EF for ending activities • LF is latest finish; EF is earliest finish • LS = LF - Activity time • LS is latest start • LF = Minimum LS of all successors for non-ending activities

  20. B D E A G 2 6 3 1 1 C F 3 4 Earliest Start Solution

  21. B D E A G 2 6 3 1 1 C F 3 4 Latest Finish Solution

  22. Compute Slack

  23. B D E A G 2 6 3 1 1 C F 3 4 Critical Path

  24. New notation • Compute ES, EF for each activity, Left to Right • Compute, LF, LS, Right to Left ES EF C 7 LS LF

  25. Exhibit 6 F 8 C 7 A 21 G 2 B 5 D 2 E 5

  26. Exhibit 6 21 28 28 36 F 8 C 7 0 21 36 38 A 21 G 2 28 33 21 26 26 28 B 5 D 2 E 5 F cannot start until C and D are done. G cannot start until both E and F are done.

  27. Exhibit 6 21 28 28 36 F 8 C 7 21 28 28 36 0 21 36 38 A 21 G 2 0 21 36 38 28 33 21 26 26 28 B 5 D 2 E 5 21 26 26 28 31 36 E just has to be done in time for G to start at 36, so it has slack. D has to be done in time for F to go at 28, so it has no slack.

  28. Gantt Chart - ES A C B D E F G 0 5 10 15 20 25 30 35 40

  29. Solved Problem 2 B4 E6 G7 C3 A 1 I4 F2 D7 H9

  30. Solved Problem 2 1 5 511 B4 E6 1118 1 5 511 G7 1118 1 4 0 1 1822 C3 A 1 I4 6 9 0 1 810 1822 F2 1 8 911 817 D7 H9 2 9 918

  31. Summary • Activity on Node representation • Calculated • ES, EF for all activities • LS, LF for all activities (working backwards) • Slack for each activity • Identified critical path(s)

More Related