Captain Andy Butterfield, USN. Deputy Mission Support Group Commander Joint Base McGuire-Dix-Lakehurst. Agenda. Mission Joint Base McGuire-Dix-Lakehurst 2005 BRAC Non BRAC Mission Partners Organization Facility Requirements Contracting Opportunities. 87 ABW Mission Statement.
E N D
Captain Andy Butterfield, USN Deputy Mission Support Group Commander Joint Base McGuire-Dix-Lakehurst
Agenda • Mission • Joint Base McGuire-Dix-Lakehurst • 2005 BRAC • Non BRAC • Mission Partners • Organization • Facility Requirements • Contracting Opportunities
87 ABW Mission Statement “To provide mission-ready Warfighters to support Unified Combatant Commanders in global military operations and unrivaled installation management for America’s only tri-service joint base.”
Joint Base Legislation • The Base Realignment and Closure Commission 2005 legislation directed the DoD to realign 26 separate installations into 12 Joint Base installations • Specifically to our installation, the legislation “realigned Fort Dix NJ and Naval Engineering Station Lakehurst NJ, by relocating the installation management functions to McGuire AFB NJ, establishing Joint Base McGuire-Dix-Lakehurst NJ”
Joint Base • Phase 1 Bases • NAS Little Creek/ Ft Story VA • Ft Myer / Henderson Hall VA • Andrews AFB / NAF Washington MD • McGuire AFB / Ft Dix / NAES Lakehurst NJ • Navy Base Guam / Andersen AB GUAM • Phase 2 Bases • Anacostia Annex / Bolling AFB DC • NS Pearl Harbor / Hickam AFB HI • Ft Lewis / McChord AFB WA • Charleston AFB / NWS Charleston SC • Elmendorf AFB / Ft Richardson AK • Lackland AFB / Randolph AFB / Ft Sam Houston TX • Langley AFB / Ft Eustis VA
Bordering Townships & Boroughs Jackson Township North Hanover Township Plumsted Township New Hanover Twp Wrightstown Borough Springfield Twp Lakehurst McGuire Fort Dix Lakehurst Borough Manchester Township Pemberton Borough Pemberton Township
BRAC Legislation • Relocate Army/Navy/Marine Units to McGuire AFB (Part 68) • Create Joint Mobilization Site (Part 144) • Establish First Tri-Service Joint Base (Part 146) FY 11 FY 05
BRAC Relocation – Part 68 • 37 Army/Navy/Marine Acft to McGuire: 57% Increase • Personnel Increase: ~700+ Full-Time, ~1500+ Part-Time • $218M+ in DoN MILCON
Non-BRAC Relocation • 23 Army Guard Aircraft moving to Lakehurst • 18 UH-60 Blackhawk Helicopters • 4 UH-72A Lakota Helicopters • 1 C-12 • Guard Personnel Increase • 100 Full-Time • 430 Part-Time • $50M+ in MILCON
JB Acft 123 95% Increase Acft 63 0 2006 2011 Combined Effects Supported Personnel ~7625 Full-time Personnel 19% Increase 6398 ~11037 Supported Personnel Part-time Personnel 34% Increase 7630 2011 2006
JB M-D-L • Number assigned grew 51% (+1,077): • Force Support Sq: 90% increase (+475) • Civil Engineering Sq: 85% increase (+316) • Contracting Sq: 60% increase (+28) • Security Forces Sq: 55% increase (+139) • Wing Staff: 46% increase (+40) • Logistics Readiness Sq: 19% increase (+64) • Area of Responsibility will increase more than 10-fold: from 3,600 acres to 42,000 acres • Number of facilities increased 8-times: from 502 to 3,933 • Value of infrastructure grew 4-times: from $2.2B to $9.3B • Number of mission partners grew approx 2.5-times: from 30 to 80 • Serviced population grew 1.5-times: from 17,000 to 41,000
Joint Base The Partners – Ft Dix • FORSCOM Power Generation Platform • Primary North East Reserve Component Training Location • Army, Army Res/NG, Navy, AF Combat Training • Contingency Operating Location (COL) — “Tiger” • Urban Assault • Convoy Ops • Combat Supt • Detainee Ops Urban Assault Training Contingency Operating Location (COL)
Joint Base The Partners – Lakehurst • NAVAIR Aircraft Launch and Recovery (ALRE) • Design/Test Catapults, Arresting Gear, Flight Deck Landing Aids • CERDEC Flight Activity Capabilities: provides sensor integration and test support on airborne platforms C-17 Assault Strip
Joint Base The Partners – McGuire • Ground Combat Skills Training • Rapid Airbase Opening • Rapid Global Mobility • Airlift • Air Refueling • Aerial Port Operations • Weapons School • Expeditionary Combat Support • Installation Management
Joint Base Vision America’s Premier Joint Warfighting Base! ARMY Mobilization Training Center Multi-service Training Range Training NAVY Research Test/Eval NAVAIR Tech Training Launch & Recovery Production USAF Rapid Global Mobility Expeditionary Combat Supt OEF Cargo Jt Base Lead Installation Support Functions
Christopher Archer Deputy Base Civil Engineer Joint Base McGuire-Dix-Lakehurst
Agenda • Joint Base Organization • Construction Projects (Recently Completed) • Construction Projects (BRAC/Ongoing) • Construction Projects (Planned) • Housing Privatization • Energy Projects • Contracting Opportunities • 87 CES POC Information
Joint Base McGuire – Dix - Lakehurst Organization Chart
Joint Base McGuire – Dix - Lakehurst Construction Projects
Success • Team -- n. A group organized to work together <a team of scientists>. vt. To harness or join together to form a team. • Partner – n. A person associated with another in a venture, occupation, or challenge. n. Either of two persons dancing with each other. v. To bring together as partners. • Success – n. The gaining of something desired, planned, or attempted.
Joint Base McGuire – Dix - Lakehurst Construction Projects (Recently Finished)
Repair Community Center, Bldg 2705 • Project completed on 6 Jun 09 • Cost: $3.3M • Project included renovation of 4 restrooms, new wall, ceiling and floor finishes, HVAC system, lighting, and fire detection/ suppression systems
Upgrade FTU Facility, Bldg 1928 • Project started: 15 Mar 08 (Design/Build Contract) • Cost: $2.06M • Completed: 27 Jul 09 • Project included new roof, brick face, exterior doors/windows, main and alternate entrances, bathrooms, auditorium, and various classrooms
Repair Base Theater, Bldg 2909 • Project completed 1 Dec 09 • Cost: $4.5M • Project Included new roof, brick face, auditorium chairs, floor and wall/ceiling/floor finishes, restrooms, concession area, and new mechanical/electrical systems
Construct ShouldersRunway 18/36 • FY 08 P-341 D/B Contract • Cost: $1.9M • Completed: 31 Dec 09 • Scope: Project constructed 25 foot wide paved shoulders; utilized crushed concrete from demo projects for stabilizing base
Construct Taxiway Hotel • FY 04 MILCON Army Reserve • Cost: $2M • Completed: 19 Dec 09 • Scope: 25 ft paved shoulders & taxiway edge lights
Completed Demos • TLF’s 2418 & 2419 (left top & bottom) • Squad Ops Bldg 2225 (center top & bottom) • Sewer Shop Bldg 1512 (right top & bottom)
Completed Demos • Alert Facility Bldg 1818 (top & lower Left) • Storage Fac 1934 (lower center) • BASH Fac Bldg 1927 (lower right and lower lower right)
Completed Airfield Demos • Transceiver Bldg 1609 (left top & bottom) • Receiver Bldg 1612 (not shown) • NDI Lab Bldg 1623 (center & right)
Joint Base McGuire – Dix - Lakehurst Construction Projects (BRAC)
Navy & Marine Corps BRAC Projects P151V/P156VNavy Hangar& Flight Simulator FY 08/09 P157VMunitionsFY 09 P162VAIMD/ASDFY 09 P161V ArmyAviation FY 09 P150VMarine Corps HeloHangar FY 08/09 P096V/P160VMarine CorpsReserve CtrFY 08
Navy & Marine Corps BRAC Projects • Marine Corps Reserve Center and NOSC Renovations • Award Amt. $23 Million • Harkins Builders, Inc., Marriotsville, MA • Completion Date: Sep 2010 • Marine Corps Helicopter Hangar & MAG 49 Hdqtrs • Award Amt. $66 Million • Boro Construction, King of Prussia, PA • Completion Date: Nov 2010
Navy & Marine Corps BRAC Projects • Navy Hangar • Award Amt. $48 Million • C. Pyramid Enterprises, Inc. Robbinsville, NJ • Completion Date: March 2011 • Aircraft Intermediate Maint Div/Aviation Supply Dept • Award Amt. $20 Million • Archer-Western Contractors, Atlanta, GA • Completion Date: Feb 2011
Navy & Marine Corps BRAC Projects • Army Reserve Aviation Facility (Hangar Renovation) • Award Amt. $9 Million • Magnum, Inc. Warminster, PA • Completion Date: Feb 2011 • Munitions Storage Igloos • Award Amt. $1 Million • Intercontinental Construction Co. Inc., Passaic, NJ • Completion Date: Oct 2010
Joint Base McGuire – Dix - Lakehurst Construction Projects (In Progress)
Repair Runway 06/24 • Cost: $40M (Includes Design to Harden Underruns) • Awarded to TOLTEST • ECD: 5 Jan 11 • Before 19 Jan 10; install fence, lighting ductwork, batch plant site work, and trailer installation. • After 19 Jan 10; finish fence across taxiways, mil runway/taxiways and use the millings to create truck haul routes.
Renovate Dorms 2622/2623 • FY08 Projects • Cost: $3.1M each (Design/Build Contract) • ECD 1 Sep 10 • Includes new wall, floor and ceiling finishes; bathroom and dayroom renovation; molded drywall replacement
AAFES Renovation • Awarded 3 Sep 09 • Cost: $4.4M; ECD: 01 Aug 10 • Project Includes: BX floors and ceiling finishes; entire food court renovation; upgrade of both entrances • Schedule: work is divided into 6 phases
Joint Base McGuire – Dix - Lakehurst Facility Requirements
FY11-15 Installation Support MILCON Projects
Security Forces Facility • FY09 MILCON Awarded Project • Cost: $6.7M (Design/Build Contract) • ECD 10 Feb 11 • Scope: 22,000 SF 2-story facility includes weapons vault, storage, administration, lockers, holding cells, bath rooms & interrogation
Sustainment, Restoration and Modernization Anticipated Annual Budget Sustainment -- Dix: $20M Sustainment -- Lakehurst: $8M SRM -- McGuire: $13M TWCF -- McGuire Minor Const: $2M TWCF -- McGuire M&R: $3.5M JB-MDL Demolition Target: $1M
Proposed FY 10 (DIX) Sustainment Priority List
Proposed FY 10 (DIX) Sustainment Priority List