05/07/12 – 5/13/12. Phase 1 Demolition at West Entry Complete; Drilled Piers and footers Started. 05/07/12 – 5/13/12. Demolition at 1927 wing nearing completion. 05/07/12 – 5/13/12. Phase 1 Air Handler Units removed. 05/07/12 – 5/13/12. Field Measured Phase 3 Rotunda
E N D
05/07/12 – 5/13/12 Phase 1 Demolition at West Entry Complete; Drilled Piers and footers Started
05/07/12 – 5/13/12 Demolition at 1927 wing nearing completion
05/07/12 – 5/13/12 Phase 1 Air Handler Units removed
05/07/12 – 5/13/12 • Field Measured Phase 3 Rotunda • Completed Electrical Shutdown to relocate Main Electrical Panel During the break… • Exterior • Complete drilled piers • Form and Pour Footings at South Side • Interior • Continue with MEP in 1927 Wing • Prep for floor cut at main electrical room • Wall off existing area at Spartan Grille to facilitate Taco Bell/C-Store Relocation NEXT WEEK LOOK AHEAD Phase 3 Rotunda Field Measurement and Verification