1 / 29

IT-390 Preliminary and Detail Methods

IT-390 Preliminary and Detail Methods. Design and Evaluation. Preliminary Estimate requested during the initial evaluation for several reasons: 1) Investigate the validity of the project 2) Clarify direction or change direction 3) To allow proper preparation. Design and Evaluation.

stacie
Download Presentation

IT-390 Preliminary and Detail Methods

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. IT-390 Preliminary and Detail Methods Ch 6

  2. Design and Evaluation • Preliminary Estimate requested during the initial evaluation for several reasons: • 1) Investigate the validity of the project • 2) Clarify direction or change direction • 3) To allow proper preparation

  3. Design and Evaluation • Preliminary Estimates - limited facts specifics • ROM (Rough Order of Magnitude) • Methods used are: • 1) Rules of thumb (heuristic approach) • 2) Simple calculations

  4. Design and Evaluation • Preliminary Estimates • less than accurate • Dollarless in value • No substantial foundation • Invaluable to continuing or terminating the operation, project, product, or system estimate in whole or part.

  5. Design and Evaluation • Detail Estimates are normally a "re-estimate” • Re-estimate of the Preliminary Estimate • More discrete information • Increased accuracy • Greater legitimacy of analysis (Mathematical/Factual)

  6. Opinion • Opinion - judgment or belief stronger than a perception, but weaker than positive knowledge. • 1) Natural part, but not uneducated ones • 2) Capable, experienced engineer - good working knowledge • 3) Natural/Planned experiences • common sense, judgment, observations, gut feelings, all of which can also be done collectively (with others).

  7. Conference • Conference is formulating an educated opinion collectively with "others". • A consensus (agreement) reached • "others" - knowledge in specific areas • engineers only - individual designs (model of estimation) • Downfall - lack of adequate analysis and verifiable facts

  8. Comparison • Similar to "Conference" but uses formal "Logic” • Compare to similar item(s)

  9. Unit • Most popular • Average • Rough Order of magnitude (ROM) • Lump sum • Module estimating • Examples of unit estimates include: • $/sq. foot (the / means “per”) • $/pound • $/machine shop man hour

  10. Learning • Idea - more often an operation is performed, less time will be required to complete it • Repetition results in less time or effort expended • The improved performance is called "Learning"

  11. Learning • Identifying Situations for Use of Learning • Not used in all situations • Must have • opportunity for improvement • reduction in labor hours per unit

  12. Learning • Use of the improvement curve should be considered in situations where there is: • A high proportion of manual labor • Uninterrupted production • Production of complex items • No major technological change • Continuous pressure to improve

  13. Learning • Factors that Support Improvement • Job Familiarization by Workers • Improved Production Procedures • Improved Tooling and Tool Coordination • Improved WorkFlow Organization • Improved Product Producibility • Improved Engineering Support • Improved Parts Support

  14. Learning • First application - manufacture of airframes • Costs lowered with increasing quantity of production or experience • Rate of improvement is 20% between doubled quantities • Therefore, learning curve is 80% or, 2nd unit will take 80% labor of what it took on 1st unit

  15. Learning • Other names for learning include: • Manufacturing progress function • Experience or dynamic curve

  16. Learning • The learning model is based on 3 assumptions: • 1) Amount of time or cost required to complete a unit of product is less each time the task is undertaken • 2) Unit time will decrease at a decreasing rate (in other words, the time reduction will slow as time moves on) • 3) Reduction in unit time follows the model y = axb (curvilinear from Ch 5)

  17. Learning • The underlying hypothesis says: "The direct labor man hours necessary to complete a unit of product will decrease by a constant percentage each time the production quantity is doubled."

  18. Learning Curve Example

  19. Learning • Several equations in this section are useful to us: • 1) Eq. • 2) Eq. 6.9, pg. 259 • 3) Eq. 6.13, pg. 261 • 4) Eq.

  20. (Ti,Ni) T Effort. Labor Rate, etc. (Tj,Nj) N Unit # Learning • Where for each, • T = effort per unit of production • N = unit number • S = slope of improvement rate, a constant • K = Constant, for unit 1, dimensions compatible to T •  = the percent learning as a decimal • These all assume that (Ni , Ti) and (Nj , Tj) are two points on a log - log curve (straight line) of "N" vs "T"

  21. Learning • Problem 6.27, pg 294, • Supplemental Problem • For the following problems, assume that the unit line is linear. • Find the first unit value when the 100th unit is 60 hours with 81% learning. • Find the value for unit 6 when unit 3 is 1000 hours with 74% learning. • If the unit value at number 1 $2000, then find the unit dollars for units 20 and 40 with learning rates of 93% and 100%. • If the cumulative average time at unit 100 is 100, then find the unit, cumulative, and average time at unit 101 for a learning rate of 92%.

  22. Learning • Calculated by regression models since data of many points are required • There are two approaches to learning curves: • 1) The Wright (cumulative average) system • 2) The Boeing (unit) system

  23. Learning • Ostwald refers to the Crawford system as the "Boeing" system • In Fig. 6.4 (pg. 258) • Two systems so it's important to know what data has been collected • Is it for unit cost or cumulative average cost? • Each requires a different system and a different set of equations

  24. Learning • Wright SystemBoeing System • cumulative average per unitcumulative average • Tá = KNs Ta = KNs /(1+s) • cumulative total effort from unit 1 - Ncumulative total • Tć= KNs+1 Tc = Tu or Tc = (Ta)(N) • unit effortunit effort • Tú = KNs+1 -K(N-1) s+1 Tu = KNs • Notes: Plot of Tá & Tu are assumed to be linear. • The “T” in Tá is for time. For cost we could have used a “C” as in Cá, but for simplicity, we will leave the equations as “T”s even when dealing with cost. N = unit number S = slope of improvement rate, a constant K= constant, for unit one

  25. Learning • Values in Appendix 5, pg. 553 • Assumption - "cumulative average" data have been collected and plotted to form the straight line in regression analysis (Wright system)

  26. Learning • Example of Wright and Boeing Methods

  27. Learning • Slope - determined from historical/predicted from experience • Minimal improvement in "hard" tooling VS manual labor

  28. Learning • Learning curve values typical of general industry groups as of 1995 were: • Aerospace 85% • Shipbuilding 80-85% • Complex machine tools for new models 75-85% • Repetitive electronics mfg. 90-95% • Repetitive machining or punch-press oper. 90-95% • Repetitive clerical operations 75-85% • Repetitive welding operations 90% • Construction operations 70-90% • Raw materials 93-96% • Purchased parts 85-88%

  29. Learning • Theoretical First Unit (TFU) Cost + an estimate of the learning curve slope = a cost estimate in (Ch 8) • 1) Risk Method - Both the TFU and learning curve slope are estimates • 2) If slope of the curve is off only +/-5%, at the 1000th unit, estimate is off by 68% • 3) The TFU cost is the cost (in dollars or man hours) to produce unit #1 • 4) "theoretical" since rarely will the cost of the first unit produced match this figure • 5) Why? Because we typically build several prototypes before reaching the 1st unit that have the effect of lowering its cost

More Related