An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MOM Report Jean-Sebastien Graulich, Geneva • Yagmur Torun (June 15 - July 14) • J.S. Graulich (July 13 - August 7) Jean-Sébastien Graulich

  2. Summary Encouraging and visible progress in the hall • Air conditioning operational • DK Solenoid cool down started • Electrical Installation • Painting • Magnet cooling water on. Soak test scheduled for next week • TOF1, KL and BPM back in place One Big Question • Will the target be ready in time One focus point • ISIS shut down: August 13 to September 15 Not much more to say • So I have included many pictures… Jean-Sébastien Graulich

  3. R78 I have tried to tidy up Please Cooperate • No more tools stored in the office • Individual paper trays Jean-Sébastien Graulich

  4. Hall Progress Electrical installation (see Andy’s talk) • Nearly finished • Fiat Lux Jean-Sébastien Graulich

  5. Hall Progress Painting • Mainly finished • Hall clean and shiny Jean-Sébastien Graulich

  6. DK Solenoid Transfer line repaired Cooling faster than in April Pierrick provided an EPICS app to ease the readings Cool down in progress (See Mike’s talk) Jean-Sébastien Graulich

  7. Detectors BPM2 TOF1 KL BPM1 Back in place • Still have to be aligned • KL offset by 20 cm due to the moving platform Jean-Sébastien Graulich

  8. Magnets Water flow is stable Hall Probe Re-discovered in R76 Water to the downstream magnets ON • One leak on Q9 had to be fixed (pressure regulator valve) Chillers tend to go on Alarm • Just because we are not enough demanding (no heat load) Marco Apollonio is preparing for soak test Jean-Sébastien Graulich

  9. Target Shafts manufactured • To be welded and coated Power electronics upgraded • New fibers pulled to MLCR The decision to install it or not will be taken on Aug 20 Jean-Sébastien Graulich

  10. Controls Pierrick is working hard to include the CAEN HV power supplies in EPICS Jean-Sébastien Graulich

  11. Conclusion We are approaching the end • Don’t stop now… Jean-Sébastien Graulich