110 likes | 208 Views
MOM Report. Jean-Sebastien Graulich, Geneva. Yagmur Torun ( June 15 - July 14) J.S. Graulich ( July 13 - August 7). Summary. Encouraging and visible progress in the hall Air conditioning operational DK Solenoid cool down started Electrical Installation Painting
E N D
MOM Report Jean-Sebastien Graulich, Geneva • Yagmur Torun (June 15 - July 14) • J.S. Graulich (July 13 - August 7) Jean-Sébastien Graulich
Summary Encouraging and visible progress in the hall • Air conditioning operational • DK Solenoid cool down started • Electrical Installation • Painting • Magnet cooling water on. Soak test scheduled for next week • TOF1, KL and BPM back in place One Big Question • Will the target be ready in time One focus point • ISIS shut down: August 13 to September 15 Not much more to say • So I have included many pictures… Jean-Sébastien Graulich
R78 I have tried to tidy up Please Cooperate • No more tools stored in the office • Individual paper trays Jean-Sébastien Graulich
Hall Progress Electrical installation (see Andy’s talk) • Nearly finished • Fiat Lux Jean-Sébastien Graulich
Hall Progress Painting • Mainly finished • Hall clean and shiny Jean-Sébastien Graulich
DK Solenoid Transfer line repaired Cooling faster than in April Pierrick provided an EPICS app to ease the readings Cool down in progress (See Mike’s talk) Jean-Sébastien Graulich
Detectors BPM2 TOF1 KL BPM1 Back in place • Still have to be aligned • KL offset by 20 cm due to the moving platform Jean-Sébastien Graulich
Magnets Water flow is stable Hall Probe Re-discovered in R76 Water to the downstream magnets ON • One leak on Q9 had to be fixed (pressure regulator valve) Chillers tend to go on Alarm • Just because we are not enough demanding (no heat load) Marco Apollonio is preparing for soak test Jean-Sébastien Graulich
Target Shafts manufactured • To be welded and coated Power electronics upgraded • New fibers pulled to MLCR The decision to install it or not will be taken on Aug 20 Jean-Sébastien Graulich
Controls Pierrick is working hard to include the CAEN HV power supplies in EPICS Jean-Sébastien Graulich
Conclusion We are approaching the end • Don’t stop now… Jean-Sébastien Graulich