210 likes | 379 Views
Pixel Construction Meeting. Stave and service integration s tatus. Staves integration status. STAVE 13 POS 07 EXTRACTION. Stave 13 has been successfully extracted on Wednesday, 19th of March. STAVE 13 POS 07 EXTRACTION. End blocks non conformity. STAVE 13 REWORK.
E N D
Pixel Construction Meeting Stave and service integration status
STAVE 13 POS 07 EXTRACTION • Stave 13 has been successfully extracted on Wednesday, 19th of March
STAVE 13 POS 07 EXTRACTION • End blocks non conformity.
STAVE 13 REWORK • The rework on both end-blocks started on Friday, 21th. • Handling frames face to face
STAVE 13 REWORK • The rework on both end-blocks started on Friday, 21th. • Module protection • Stave transfer
STAVE 13 REWORK • The rework on both end-blocks started on Friday, 21th. • Tool implementation
STAVE 13 REWORK • The rework on both end-blocks started on Friday, 21th. • Ready to cut
STAVE 13 REWORK • The rework on both end-blocks started on Friday, 21th. • After cutting
STAVE 13 REWORK • The critical rework of both end-blocks thanks to the design work of Eric V., Augusto C. and the expertise of Maarten W. was very fluent.
STAVE 13 POS 07 RE-INTEGRATION • Stave 13 was successfully re-integrated on the IBL package on Friday, 21th.
STAVE 19 POS 03 INTEGRATION • Stave 19 was successfully integrated on the IBL package on Monday, 24th. • End blocks on both sides were machined with a very low planarity
STAVE 02 POS 02 INTEGRATION • Stave 02 was successfully integrated on the IBL package on Wednesday, 26th.
STAVE 17 POS 01 INTEGRATION • IBL staves integration completed successfully with stave 17 on Wednesday, 26th.
TASKS TO COMPLETE THE PACKAGE A huge step forward but still a lot to do before the IBL completion (Didier F. PP0) • Stave integration completion – Until March 27th • Monday 24th: Integration of stave at position Phi #3 • Wednesday 26th morning: Integration of stave at position Phi #2 • Wednesday 26th afternoon : Integration of the last stave – Stave #17 • Thursday 27th : Last electrical connectivity tests • Engineering on IBL by 1 single rotation – March 27th to April 3rd • Mushroom + glue drops on A and C sides (alternate every two staves) • Spring loaded screws on A-side – securing system with either Loctite222 or Epoxy has to be tested • Central ring including tooling (test on mock-up to be considered) • Lacing of I-Flex region (to be discussed with FX) • Kapton foil protection on Type 1 15
TASKS TO COMPLETE THE PACKAGE IBL mushroom Spring system Side A
TASKS TO COMPLETE THE PACKAGE Central ring
TASKS TO COMPLETE THE PACKAGE • Sealing rings and Wifi RH sensors – April 4th to 8th • Z-translation of IPT by +2 and -2 cm for these steps • Fill sealing ring openings with PUR glue and enclose with a Teflon collar • Repeat the operation on the other side after sliding the IBL package • Insertion of the 4 Wifi RH sensors inside the IBL package • Electrical tests of the 14 staves before or after closure (1 day) • IST closure and Humidity tests – April 9th to 24th • Envelope check and MPC closure • Sealing ring clamp and seal the overall IST along the 7m with kapton tape • Flushing of N2 + RH measurements and cross-calibrations (15 calendar days) 18
TASKS TO COMPLETE THE PACKAGE • Service wrapping – April 11th to 24th • Beam pipe extender installation • Service wrapping on A and C sides • Removal of service wheels • Final IBL closure – April 24th to April 30th • MPC extension connection • Sealing of package plus flushing and reading of the Wifi humidity sensors • Contingency of 1 day plus one week-end beginning of May • Movement to loading area and Transport to SX1 – May 5th (depending of the weather) • NB: • All the testing meaning: connectivity tests and relative humidity measurements must be in phase with the above engineering work (coordination by Alessandro and Daniel) 19
TASKS TO COMPLETE THE PACKAGE • NB: • Any information above is based on discussion this morning with Sebastien + some last modification/shortening proposed by me to match the completion by end of April • Any request to reduce/change task should be made to Sebastien/Franck