LCLS Injector/BC1 Commissioning

This document provides a timeline and manpower requirements for the commissioning of the LCLS Injector/BC1, including installation, testing, and beam characterization phases.

teixeira
Download Presentation

LCLS Injector/BC1 Commissioning

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Injector/BC1 Commissioning(Jan. 2006 through Aug. 2007)P. Emma, et al.LCLS DOE ReviewOct. 25, 2006 LCLS http://www-ssrl.slac.stanford.edu/lcls/internals/commissioning/index.html

  2. Commission in Jan. 2008 Commission in Jan. 2007 LCLS Accelerator Schematic 250 MeV z  0.19 mm   1.6 % 4.30 GeV z  0.022 mm   0.71 % 13.6 GeV z  0.022 mm   0.01 % 6 MeV z  0.83 mm   0.05 % 135 MeV z  0.83 mm   0.10 % Linac-X L =0.6 m rf= -160 Linac-0 L =6 m rf gun L0-a,b Linac-3 L 550 m rf  0° Linac-1 L 9 m rf  -25° Linac-2 L 330 m rf  -41° 25-1a 30-8c 21-3b 24-6d ...existing linac 21-1 b,c,d undulator L =130 m X BC1 L 6 m R56 -39 mm BC2 L 22 m R56 -25 mm DL1 L 12 m R56 0 DL2 L =275 m R56  0 SLAC linac tunnel research yard

  3. Complete & Detailed Optics (cathode to dump) dump cathode L3 L2 BC2 LTU undulator sec-21 sec-30 Full MAD files at: http://www-ssrl.slac.stanford.edu/lcls/linac/optics/

  4. LCLS Installation and Commissioning Time-Line Drive-Laser Commissioning LTU/und. Install LTU/und. hall “ready” Drive-Laser Installed Controls Checkout First Spont. Light A S O N D J F M A M J J A S O N D J F M A M J J 2006 2007 2008 Gun/Inj./BC1 Install (8/21 – 2/20) Gun/Inj./BC1 Commissioning linac/BC2 Commissioning linac/BC2 Install LTU/und. Commissioning Oct. 18, 2006

  5. LCLS Injector Commissioning Dates (2006 - 2007) Dec 18: PPS Certified Dec 20-Jan 1:Holidays Jan 2: VVS’s switched on for PEP-II (RF power available) Jan 15: L0a, L0b, L1 RF processing begins Feb. 1: X-band RF processing begins Feb 20: GTL beamline installation complete Mar 6: Virtual cathode fully characterized (ready to install gun) Mar 7: RG gun installation begins – laser rate to 30 Hz Mar 16:First laser UV-light on cathode! Mar 17: Electrons in GTL and gun-spectrometer Apr 9: Beam through L0a, L0b and down to 135-MeV spectrometer Apr 24: Beam into main linac (to TD11 dump) ~July: Take beam down full linac (to BSY SL2 stopper) http://www-ssrl.slac.stanford.edu/lcls/internals/commissioning/documents/commissioning-dates-2006-2007.ppt

  6. Commissioning Definition and Strategy All components installed, aligned, connected, and initially verified by system engineer, before commissioning starts. • Commissioning Sequence – Layered Approach (0-3) • 0. Pre-Beam Checkout (tunnel, gallery, control room) • Controls/software testing, camerachecks, beamline inspection, etc • Magnet polarities, cable connections, verify motion-control, etc • Beam-based Hardware and Software Checkout • Establish beam transport, RF setup, MPS/BCS tests, etc • Checkout of all BPMs, magnets, wires, screens, toroids, etc • First-Order Optics: Measurement and Correction • Steering, transmission, oscillation data, feedback setup, etc • Beta and dispersion matching, beam-base align key quads, etc • Full Beam Characterization: Measurement and Correction • Measure emittance, energy spread, distributions - correct • Measure beam sensitivities, optimize tuning, beam experiments No (serious) emittance measurements until all hardware/software checked out!

  7. (detailed schedule available) pass-1 pass-2 pass-3 pass-1 pass-3 pass-2

  8. http://www-ssrl.slac.stanford.edu/lcls/internals/commissioning/documents/2007-commissioning-plan.dochttp://www-ssrl.slac.stanford.edu/lcls/internals/commissioning/documents/2007-commissioning-plan.doc

  9. LCLS Injector Commissioning Day 24-Hour Cycle (7 days/week, 1/2/07 to 8/31/07, 35 total weeks) DAY SHIFT (8:00-16:00) 1 lead physicist, 1 physicist, 1 controls eng., 1 sys. engineer, 1 LCLS operator, 1 laser operator SWING SHIFT (16:00-24:00) 1 lead physicist, 1 physicist, 1 LCLS operator, 1 laser operator OWL SHIFT (0:00-8:00) 1 LCLS operator, 1 laser operator ?

  10. Personnel Available for LCLS Injector/BC1 Commissioning • Shift Leaders(initially) • (1 per D/S shift) • Dave Dowell • Paul Emma • Jim Turner • Bill White (laser) • Joe Frisch • Cecile Limborg • Controls eng. • (1 per DAY shift) • Stephanie Allison • Mike Zelazney • Debbie Rogind • Diane Fairley • Stephen Norem • Arturo Alarcon • Doug Murray • Sergei Chevtsov • Dayle Kotturi • Patrick Krejcik • Kristi Luchini • Sheng Peng • Stephen Schuh • Till Straumann • Sys. Engineers • (1 per DAY shift) • Eric Bong • Carl Rago • Leif Eriksson • Richard F. Boyce • Jose Chan • Tim Montagne • Paul Bellomo • Antonio de Lira • Dave MacNair • Ron Akre • LCLS Physicists • (1 per D/S shift) • Sasha Gilevich • Henrik Loos • Heinz-Dieter Nuhn • John Schmerge • Dave Schultz • Jim Welch • Juhao Wu • Accelerator, ILC, SSRL • Franz-Josef Decker • Rick Iverson • Doug McCormick • Jeff Corbett • James Safranek... Operations (1 per DAY & SWING shift and 2 per OWL) Laser Operators (4-5) Visitors ?

  11. Manpower Requirements (1/2/07 - 8/31/07) • 35 weeks total (1/2/07 to 8/31/07, minus 2 weeks) • 80% coverage (downtime) • 14 lead-physicist shifts/week • 14 physicist shifts/week • 7 controls eng. shifts/week • 7 sys. engineer shifts/week • Average of 2-3 shifts/week for each physicist • Average of 1/2 shift/week for each controls eng. • Average of 1 shift/week for each sys. engineer

  12. LCLS Commissioning Parameters

  13. Issues • Controls will be mixed (SLC, Epics, Matlab) and capabilities may be limited initially (H. Shoaee) • Most High-Level Applications (emittance, bunch length, feedback) done through MATLAB as temporary solution • Many LCLS physicists not experienced with existing SLC controls • Help from operations group is essential

  14. RF Photo-Cathode Gun • Q 1 nC • f 120 Hz • G 120 MV/m • gex,y 1 mm • Dt 10 ps • I 100 A • E 6 MeV e- spec. dipole e- UV laser solenoid YAG screens RF gun cathode

  15. YAG screen RF Gun • trajectory (BPMs) • emittance (+ slice) • energy spread (+ slice) • bunch length (+ dist.) • charge (+ dark current) YAG screen YAG screen YAG screen YAG screen gun spectrometer Transverse RF deflector OTR & wire Injector Diagnostics OTR & wire OTR & wire OTR & wire main SLAC Linac injector spectrometer YAG YAG & OTR

  16. Injector Through BC1 RF Gun & Solenoid L0a&L0b S-Band Linacs Transverse RF Cavity Bunch-Compressor-1 (BPM, OTR, collimator) OTR & Wire Scanners Gun Spectrometer L1 S-Band Linac Wire Scanners + OTR 135 MeV 250 MeV TD-11 stopper X-Band RF Straight Ahead Spectrometer Bunch Length Diagnostics 40 m

  17. Accelerator Sections Straightened Coordinate Measurement Machine (CMM) after before (De/e 30%) Four RF sections measured on CMM and straightened (L0a, L0b, L1a, L1b) Jose Chan

  18. Magnet Polarities Defined and Documented DIPOLES QUADRUPOLES SOLENOIDS

  19. BPMs, Wire-Scanners, etc. Polarities Defined BPMs: Wire-Scanners: q = 0 q = +45º q = -45º q = +45º

  20. All Magnets Measured (all steering coil ‘types’) • 2 Solenoids • 19 Inj. Quads • 2 GTL Quads • 2 BC1 Quads • 3 Linac Quads • 2 DL1 Dipoles • 4 BC1 Dipoles • 2 Spect. Bends • 6 corr. types Dipole field vs. x Current vs. integrated field Solenoid eff. length FINT = 0.454 Dipole fringe field vs. z + field harmonics

  21. BC1 Chicane tweaker quad 2 0-30 cm translation stage tweaker quad 1 OTR X-band RF collimator BPM

  22. BC1 Dipole Fields are Marginal tracking through fields measured with stretched wire De/e0 1 to 6 % Pole nose pieces in fabrication + tweaker quadrupoles available

  23. Dispersion Correction in SPPS Chicane One linear comb. of 2 tweaker quads

  24. Pre-Beam Tunnel Check List etc.

  25. Summary • Injector e- commissioning starts Mar. ’07 • Main ’07 goal is to verify full functionality of gun, injector beam-line, diagnostics, and controls, not generate full beam brightness immediately • Will need frequent linac access initially (8-16 hrs/week?) + 1 install-day per month (24-48 hrs?) • Phase-II of commissioning comes in Dec. ’07 • Information available at commissioning web-site: http://www-ssrl.slac.stanford.edu/lcls/internals/commissioning/index.html