An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ODOT WELCOME! District 1 & District 2 October 28, 2013

  2. Purpose of toDAY’s meeting • Provide a project overview • Present Update for HAN-224-11.81 • Present MOT for HAN-75-14.39 & Proposed Roundabouts on Lima Ave. • Present D2 update on I-75 north of Findlay • Listen to your input

  3. HAN-224-11.81 • IR-75/US-224 interchange status: • $11.5 Million funded with Turnpike Funding • Independent project • 2014 construction

  4. Project Overview – HAN-224-11.81 • Reconstruct of I-75 interchange with USR 224 • Reconstruction and widen of bridge • Adding lanes • Turn Lanes on and off bridge • Replacing existing signals

  5. Maintenance of traffic HAN-224-11.81 • Part-width construction • One lane in each direction • Closures/Detours: • Short duration closures of ramps and USR 224 • Short term use of ramps to maintain I-75 traffic

  6. Project overview – han-75-14.39

  7. Project Overview – HAN-75-14.39 • Construction scheduled for 2017 but could begin as early as 2015 • Reconstruct & widen I-75 to 6 lanes • New Right-of-Way Required • Began to purchase R/W Feb. 2013 • Current Estimated Construction Cost: $150 Million

  8. Project Overview – HAN-75-14.39 • Harrison St overpass reconstructed • Lima Ave interchange reconstructed with US68/SR15/IR75 interchange • New Service Rd near ODNR • Roundabouts on Lima Ave at ramps

  9. Project overview – han-75-14.39 • The following overpasses will not be replaced as part of this project: • CR 88 – Sandusky Street • SR 12 – Main Cross Street • US 224 – Construction 2014 • CR 95 – Bigelow Avenue • CR 99

  10. Maintenance of traffic HAN-75-14.39 • MOT is preliminary at this time • Project separated into Four Zones • 3 MOT Methods • Maintaining 2 lanes each direction on I-75 and 1 lane each direction on US68/SR15 • Hybrid Method – System to System Interchange

  11. Maintenance of traffic HAN-75-14.39 – mot zones

  12. MOT - typical sections(Zone 3 – part-width)

  13. Han-75-14.39 – hybrid mot

  14. i-75 north to us68/sr15 & lima ave

  15. i-75 south to us68/sr15 & lima ave

  16. us68/sr15 & lima ave to i-75 north

  17. us68/sr15 & lima ave to i-75 south

  18. Lima ave to & from us68/sr15

  19. Lima ave to & from us68/sr15

  20. i-75 area north of us68/sr15

  21. lima ave - roundabouts

  22. I-75 North of Findlay • Multiple projects funded with turnpike revenue • Reconstruction & widen of I-75 from two to three lanes in each direction • From County Road 99 in Hancock County to I-475 in Wood County • Distance of 31.6 Miles • Estimated Total Cost: $220 Million

  23. I-75 North of Findlay

  24. I-75 North of Findlay • Widening will take place in the existing median • Median width 84’ for the north 2/3 of the project length and 50’ - 60’ for south 1/3 of the project • Cable barrier north of Cygnet Road, concrete barrier south of Cygnet Road • Two lanes of traffic will be maintained throughout the duration of the project

  25. I-75 North of Findlay: North Baltimore • CR 95 to Oil Center Rd. • Design Build Project • Estimated Cost: $55M

  26. I-75 North of Findlay: Oil Center Rd. to Portage Rd. • Estimated Cost: $50M

  27. I-75 North of Findlay: Bowling Green • Portage Rd. to Devil’s Hole Rd. • Estimated Cost: $55M

  28. I-75 North of Findlay: BowlingGreen – US 6 & I-75 ABC

  29. I-75 North of Findlay: Bowling Green • Devil’s Hole Rd. to I-475 • Estimated Cost: $60M

  30. I-75 North of Findlay: • Construction: Start 2014 • Construction complete: 2016 • I-75 North of Findlay District 2 Contacts: • Aaron Behrman, ODOT District 2, Design Engineer • Phone No.: (419) 373-4402 • Mike Stormer, ODOT District 2, Planning Engineer • Phone No.: (419) 373-4472