1 / 20

Landfill Gas Migration Control

Landfill Gas Migration Control. A Design-Build Success Story Dick Sprague HDR, Inc. Purpose & Background. Design-Build Project Delivery Emerging delivery system in public sector Single source of responsibility Faster, less contentious delivery Not necessarily cheaper Landfill

vangie
Download Presentation

Landfill Gas Migration Control

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Landfill Gas Migration Control A Design-Build Success Story Dick Sprague HDR, Inc.

  2. Purpose & Background • Design-Build Project Delivery • Emerging delivery system in public sector • Single source of responsibility • Faster, less contentious delivery • Not necessarily cheaper • Landfill • Historic landfill cell began in early 1950s • New, lined landfill cell began in late 1990s • Landfill gas migration discovered in 2001

  3. Landfill Site

  4. Landfill Gas Migration • Anaerobic decomposition • Predominantly methane and carbon dioxide • March 2001 monitoring • High concentrations of Lfg at property boundary • >1,000 feet beyond property boundary • May 2001 • Issued engineering RFP • Informed state agency & neighbors

  5. Extent of Contamination

  6. Design-Build Project • Too little time for traditional design-bid-build • 2-part contract • Several form contracts • AGC, AIA, EJCDC • DBIA is fairest to all parties • 2-Part form contract includes: • Terms & Conditions • Scope • Price & Schedule

  7. Design-Build Project (cont.) • Part I - Concept Design & Proposal • 30% Design • Proposal for Part II • Firm, fixed price based on bids • Drilling subcontractor • Equipment supplier • Balance of construction contractor • Documents Belong to Owner • Negotiate with Part I contractor • Bid the work • Cancel the project

  8. Design-Build Project (cont.) • Part II • Final Design • Construction, Start-up & Warantee • Firm schedule based on WES commitments • Contract (part II) signed on September 27 • Completion planned for December 14 • “Best Value” Selection

  9. Design-Build Project (cont.)

  10. Design-Build Project (cont.) • Performance • Drilling subcontractor failed to perform • Primarily his lower tier subs • Third lower tier sub required to complete project • Flare station operational December 14, accepted December 18 • 60 percent of wells operational on December 18; met commitment to state agency • Final completion January 18

  11. Design-Build Project (cont.)

  12. Design-Build Project (cont.)

  13. Design-Build Project (cont.)

  14. Design-Build Project (cont.)

  15. Design-Build Project (cont.)

  16. Design-Build Project (cont.) Lump Sum Price Change Orders Net Price

  17. $929,367 ($ 25,129) _________ $904,238 Design-Build Project (cont.) Lump Sum Price Change Orders Net Price

  18. Questions?

  19. Design-Build Project (cont.)

More Related