1 / 20

Changes in Operating Duty & Impact on RAM

Changes in Operating Duty & Impact on RAM. Bob Steele. March 7, 2007. Industry Changes. Significant Changes in Market over past 10 to 15 Years Changes in Anticipated Demand Environmental Concerns Fuel Prices Others…

venecia
Download Presentation

Changes in Operating Duty & Impact on RAM

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Changes in Operating Duty & Impact on RAM Bob Steele March 7, 2007

  2. Industry Changes • Significant Changes in Market over past 10 to 15 Years • Changes in Anticipated Demand • Environmental Concerns • Fuel Prices • Others… • Review How These Changes Have Impacted… Operating Profile and RAM (Reliability, Availability, and Maintainability) • Based Upon Data From ORAP • Review Generic Aero-derivative Market Data (Not Specific to GE Engines)

  3. Base ORAP® • ORAP - Operational Reliability Analysis Program • Service provided to • Owner/Operators • Original Equipment Manufacturers (OEMs) • Monitors Reliability, Availability and Maintainability (RAM) • Adheres to Industry Standards: IEEE Std. 762 and ISO 3977 • Gas Turbine, Steam Turbine and All Related Plant Equipment

  4. Base ORAP® • Proprietary Database • Contains 20,000 Unit Years of Operating Information from 2,000 Units Around the World • Operating, Maintenance, and Failure Information on Total Plant Equipment • Proprietary Equipment Breakdown Structure (EBS) • Common Coding Structure for Equipment and Components Across Different Fleets and OEMs • Equipment Hierarchy • Major System Down to Individual Components

  5. P&W Power Systems Steam Turbine OEMs ALSTOM General Electric Rolls-Royce Siemens Base ORAP® Participation Includes FT8 FT4 501 AVON TRENT RB211 LM6000 /DLE LM5000 LM2500 /DLE LM1600 LM500 MS5001 MS6001B-FA MS7001B-FA MS9001B-FA W251 W501AA-FD V84.2 V84.3A V94.2 Size: 2 MW to >700 MW GT11D GT11N-N2 GT13-E2 GT8B-C GT9 GT24 GT26 FOSSIL ST Covers Simple & Combined Cycle Arrangements, Including Steam Cycle

  6. Change In Operating Profile Source: ORAP®; All rights reserved: SPS® • Over 40% Reduction in Annual Service Hours from 1995 to 2006 • On Average Aero-derivative Market Operating More in Cycling Duty During the Last 5 years

  7. Gas Price Influence • Change in Duty/Operating Profile – Follows Increasing Costs of Natural Gas

  8. Availability & Reliability Source: ORAP®; All rights reserved: SPS® • Decrease in Availability and Reliability During Period of Transition to Cycling Duty Occurs (~1998 – 2001) • Fairly Consistent Reliability and Availability in Last 5 Years

  9. Duty Cycle Impact – Service Factor Source: ORAP®; All rights reserved: SPS® • All Duty Cycles Have Experienced a Decrease in Annual Service Hours in Most Recent 5 Year Period • Cycling Duty Units Decreased ~30% - Approximately 950 Service Hours per Year

  10. Duty Cycle Impact – Service Hours/Start Source: ORAP®; All rights reserved: SPS® • Annual Service Hours per Start Also Decreases Across All Duty Cycles in Most Recent 5 Year Period • Cycling Duty Units Decreased to ~12.9 Hours per Start – Indicative of Daily Start/Stop Operation

  11. Duty Cycle Impact – Output Factor Source: ORAP®; All rights reserved: SPS® • Output Factor Representative of Average Unit Load During Operation • Decreased Output Factor – Not Only are Units Operating Less, Also Operating At Lower Load Levels

  12. Duty Cycle Impact - Availability Source: ORAP®; All rights reserved: SPS® • On Average, Availability Higher Across all Duty Cycles for Most Recent 5 Year Period • As Cycling Duty Has Become More Prevalent, RAM Performance has Improved Significantly – Still Lower Than Any Other Duty Cycle

  13. Duty Cycle Impact – Unplanned Events Source: ORAP®; All rights reserved: SPS® Source: ORAP®; All rights reserved: SPS® • Slight Reduction in Frequency of Unplanned Events Over Last 5 years (Increased Time Between Events). • Unplanned Events Still Occur Over Twice as Frequently on a Service Hours Basis on Cycling Duty Units than Baseload Units. • Significant Decrease in Average Duration for Cycling Duty Units as Number of Units Operating in this Manner Increased

  14. Duty Cycle Impact – Engine Removals Source: ORAP®; All rights reserved: SPS® • Engine Removals Occur More Frequently on Cycling Duty Units • Planned Removals Occur Over 50% More Frequently on Cycling Duty than Baseload Duty • Unplanned Removals Occur ~37% More Frequently on Cycling Duty than Baseload Duty

  15. Summary of RAM Performance • Number of Units Operating in Cycling Duty Increasing • RAM Performance has Improved in Most Recent 5 Years • Cycling Duty More Severe than Other Operating Modes • Significant Growth in Availability Performance in Last 5 Years • Function of Reduced Downtime per Event • Change In Operating Profile to Cycling Duty Highlights the Need for CPLM/Cycles Tracking • Daily Start/Stop Operation Increasing – Service Hours per Start Averaging 12 Hours per Start for Cycling Duty Units • Reduction of Output Factor – Indicative of Increased Load Following Across All Duty Cycles – Partial Cycles

  16. ORAP Automated Cycles Tracking™ • Last Year Presented SPS Solution for Automated Cycles Tracking… • Automatically detects and logs every Full, Partial and Trip Cycle as it occurs • Transfers the cycles data (via Internet connection) to the SPS Data Center • Accumulated cycles calculations performed and applied to the appropriate parts • Through ORAP Interactive™ detailed reports can be run and parts age/accumulated cycles tracked

  17. ORAP Automated Cycles Tracking – Status • Initial Remote Data Collection Module Installed • Control System Connectivity Verified • Network Security and Data Transfer Challenges Resolved • Algorithms Validated • Several Bugs Identified and Addressed • Calculates Full, Trip and Partial Cycles in ‘Real Time’ • Enhancements Identified • ‘Heart beat’ being implemented to ensure Communications Link During Periods when Unit Not Operating • Second System Currently Being Readied for Installation

  18. ORAP Cycles Tracking - Cont Cycles Tracking Summary – Web Based Report

  19. ORAP Cycles Tracking - Cont Cycles Tracking Details – Web Based Report

  20. Thank You