Searching for the QGT : Q uantum Efficiency G ain T ransparency

Searching for the QGT : Q uantum Efficiency G ain T ransparency. Stony Brook Crew & BNL Crew. Summary in Brief: Quantum Efficiency. The GEM was evaporated on Monday April 3 The Local QE test looks basically normal (a bit above average) Flash Lamp tests same today as initial installation:

vondra
Download Presentation

Searching for the QGT : Q uantum Efficiency G ain T ransparency

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Searching for the QGT:Quantum EfficiencyGainTransparency Stony Brook Crew & BNL Crew

  2. Summary in Brief: Quantum Efficiency. • The GEM was evaporated on Monday April 3 • The Local QE test looks basically normal (a bit above average) • Flash Lamp tests same today as initial installation: • April 6: 475 mV in CF4 (only 6.7 turns of detector) • April 10: 514 mV in CF4

  3. Summary in Brief: Gain • A number of gain curves weretaken prior to replacing the grid. • One anomalouslow-gain scan wasseen (detail later) • With gain replaced and operating via a resistor chain the SUPER WEAK source still shows 55Fe peak. Present State

  4. Summary in Brief: Transparency. • Levels presently in HBD prototype: • 14 ppm water. • 22 ppm oxygen. • Presently low flow to conserve CF4 • Easy to achieve < 10 ppm each… • Water cost in photo-electrons: • ~1 p.e./ 10ppm of water

  5. Executive Summary: • HBD could be installed into IR immediately with good operation. • BUT!!!...we can do better… • More detailed history of test follows…

  6. Detailed History #1: • Monday April 3: Evaporation followed by overnight purge of Italian Glove Box: • Glove box purging with Nitrogen. • Evaporation box purging with Nitrogen. • HBD purging with Argon.

  7. Detailed History #2 • Tuesday April 4: Install GEMs into the HBD prototype: • Smooth installation (grabber tools effective) • GEM-GEM-CsI-GRID-SPACER-55Fe (strong) • Leave under CF4 purge overnight. • ppm levels into teens in ~6 hours with high flow.

  8. Detailed History #2 • Wednesday April 5: • Transparency reference with Flash Lamp:475 mV into 50 ohm in CF4 (w/o diffuser) • See 55Fe pulses and take first spectra. • Spectra are BEAUTIFUL!!! • Trouble: Corona discharge from GRID. • Take Spectra late into the night…

  9. Detailed History #3 • Thursday April 6: Demonstrate Corona is gridground (not grid top GEM). • Decision: Grid must come out for repair. • Friday April 7: • Flash lamp test shows usual performance. • After flash lamp (surprise) top GEM not infinity ohm…attributed to charge on GEM (wrong). • Grid comes out…found a few mm long “hairs”. • Grid gets beard trim & overcoat w/ epoxy. • After cure, gridHigh Vacuum • Saturday: GridGlove Box. • Sunday: Re-assemble: • GEM-GEM-CsI-SPACER-GRID-Weak Source. • OUCH!! Top GEM still shows current draw… 11.8 MOhm.

  10. Detailed History #4 • Monday April 10: • Rewire the dividerchain to account for shorted strips. • Wimpy source needsLONG integrationto see signals. • Two-pronged attack: • Keep present HBD. • Fresh GEM in evaporator. • Evaporate today;make decision soon: • Swap the GEM. • Swap the source back.

  11. Another note • We were contacted by glove box company. • DELAY!!! • They would like to install Glove Box May 31. • We demanded that contract says last date is May 12. • Negotiating temporary solution: • Deliver Glove Box with “standard” (smaller) air-lock. • Transfer GEMs from Evaporation box to secondary container using Italian GB. • Expect further contact today.

  12. Status of the IR • Gas Lines are in place. • Ar flow since March 27. • Analyzers installed Friday April 7. • Still needs calibration… • LV and HV should be in place this week. • 4 hours access • Mechanical Support: • Don Lynch will use “Skill of the Craft”… • Fastened to MVD table on its back. • Pressure/Temp/Ancillary Stuff installed. • Hey Chi!!! • How about that electronics???