The Retrocommissioning (RCx) program aims to maximize performance efficiency by optimizing existing building systems. This program at UBS 677 Washington Blvd in Stamford, CT achieved significant energy savings, cost savings, and established an eco-friendly corporate culture. Future goals include LEED certification and expanding RCx to all facilities.
E N D
Retrocommissioning Program UBS 677 Washington Blvd, Stamford, CT
Definition • Retrocommissioning (RCx) is a program that seeks maximum performance efficiency through the optimization of existing building systems.
Ideal RCx Candidate • Good Building Management System • Well maintained facility • Good record documentation • Knowledgeable operations staff • Good vendor relationships • Willingness to collaborate
RCx Process • Phase 1 • Scoping study • RCx investigation • Phase 2 • Recommendations and priorities • RCx implementation • Phase 3 • Verification of results • Persistence monitoring • Documentation • Training
Goals of RCx Program • Energy savings • Cost savings • Establish an eco-friendly corporate culture • Future development of workable cost-effective solutions
677 Washington Blvd • Major Financial Center Occupying 1.4 MM SQ-FT • Trading Operations – 125,000 SQ-FT • Mission Critical Data Center – 30,000 SQ-FT • Offices – 600,000 SQFT • Kitchen/Cafeteria – 35,000 SQ-FT • Atrium – 13,000 SQFT • Parking – 640,000 SQ-FT • Energy profile of 48 MM kWH per year
RCx Findings • Central Plant & HVAC Systems • Chilled water temperatures operated on a fixed scale. • “Free” cooling was part of a scheduled program. • Many of the pumps were driven by constant speed motors regardless of demand. • Obvious inefficiencies in the piping system. • Excessive electric heat – 2 mW. • Lighting Systems • Inefficiency of the dimming system on the trading floor. • Garage lighting operating on a 24x7 basis. • Excessive off-hours lighting.
Target Reductions • Electrical • Consumption kWH: 5 to 10% Reduction.
RCx Examples • Piping Upgrades • Condenser water flow control upgrades were made through changes in operation as well as the elimination of extraneous piping loops. • Central Plant Equipment Upgrades • Many of the motors used for primary pumping were optimized for variable speed drives. • Lighting Upgrades • Dimming systems optimized in the trading area and atrium. • Off-hours lighting controlled by sensors that are linked time clocks.
Results • Overall per month reduction of 3,840,000 kWH (average). • Overall annual cost savings of $614,000. • CO2 reduction of 1,106 tons.
Future Goals • Incorporation into our LEED certification program. • Initiate RCx for all facilities.