1 / 17

BIS and SMP activities during LS1

BIS and SMP activities during LS1. TE-MPE LS1 Workshop S. Gabourin on behalf of TE-MPE-EP. 1 – BIS and SMP : Change CPU Modules in VME systems (#11115, #11117 and #11119). Description of the activity

wyatt
Download Presentation

BIS and SMP activities during LS1

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BIS and SMP activities during LS1 TE-MPE LS1 WorkshopS. Gabourinon behalf of TE-MPE-EP

  2. 1 – BIS and SMP : Change CPU Modules in VME systems (#11115, #11117 and #11119) • Description of the activity • For all VME systems, replace the RIO3 modules (LynxOS) by the MEN-A20 modules (Linux). The latter are supplied by BE/CO • The VHDL firmware of the VME boards needs to be adapted to the MEN-A20 • The FESA class has to be adapted • The VME systems crates are • BIC installed around the LHC ring, in the Injection and Extraction regions and in the SPS ring (~40 front-ends have to be upgraded) • SMP controllers installed in the CCR (2 front-ends) SMP

  3. 1 – BIS and SMP : Change CPU Modules in VME systems (#11115, #11117 and #11119) • Why during LS1? • LynxOS power PC are no longer supported by BE/CO • Risks / impact if not during LS1 • Not enough spare to replace faulty RIO3 modules in operation • No support if any malfunction → Loss of monitoring • Time period • Before August 2013 • 2 weeks for installation (4 CPU / day) • Manpower • Stéphane to replace the modules in the alcoves and check if the monitoring works • Contribution of MS section to adapt the FESA class • Contributions from the other groups • The MEN-A20 boards are provided by BE/CO group. • Potential showstoppers • Delay for supplying the MEN-A20 from BE/CO

  4. 2 – BIS : Install fiber optic monitoring for the Beam Permit Loops (#11124) • Description of the activity • Monitor the optical signals, and anticipate false dumps due to a decreasing of the optical budget • The prototype module will be installed on spare fibers (1 or 2) • Several configurations can be implemented for monitoring (Raspberry PC, Python interface…) • Why during LS1? • Some fibers optic show an important attenuation of optical budget since their installation • Risks / impact if not during LS1 • Beam permit not correctly transmitted on the BIS loops → False Beam Dump • Time period • Before August 2013 • 1 day for the installation • Manpower • Jonathan and Spyros (and MS?) • Contributions from the other groups • None • Potential showstoppers • None

  5. 3 – BIS : Replace the CIBF units (#11125) • Description of the activity • Upgrading of the CIBF units. They are mainly used for the SPS Extraction / LHC Injection User Permits (Experiments and LBDS links). In total 38 pairs of CIBF are in operation • At least the CIBT board (used for monitor and test the CIBF) needs an upgrade. • Why during LS1? • Lack of monitoring • Not possible to remotely measure the optical power • Obsolescence of the components • Risks / impact if not during LS1 • Diagnostics issues → Loss of availability • CIBF spare limited (due to obsolescence) • Time period • Before Feb 2014 • Manpower • Stéphane • Contribution of MS (FESA and Java GUI follow-up) Optical link CIBFu CIBFc User system

  6. 3 – BIS : Replace the CIBF units (#11125) • Contributions from the other groups • None • Potential showstoppers • Depending on the design study, there will be more impact on existing cards → Design a new CIBTand potentially a new CIBM User system CIBU Optical link CIBFu CIBFc User system

  7. 4 – BIS : Deploy a BIS for Linac4 (#11123) • Description of the activity • 3 BICsand about 25 CIBUlinks have to be installed and commissioned. • Why during LS1? • The installation has to follow the Linac4 schedule • Risks / impact if not during LS1 • Stop the progress of Linac4 project • Time period • Before August 2013 • Manpower • Christophe, Stéphane and Nicolas • MS: Instantiate FESA and BIS GUI for new FECs • Contributions from the other groups • All L4 equipment systems connected to the BIS • Potential showstoppers • The Linac4 planning

  8. 5 – BIS : Move a BIC from UJ56 to USC55 (#11126) • Description of the activity • A Beam Interlock Controller needs to be moved from UJ56 to USC55 • Why during LS1? • Radiation issue • Risks / impact if not during LS1 • R2E problems after LS1 • Time period • Before August 2013 • Few days • Manpower • Christophe and Nicolas • Contributions from the other groups • EN/EL to install fibers in USC55 • Potential showstoppers • None

  9. 6 – BIS : Re-commission CIBU users who will make change during LS1 (#11126) • Description of the activity • If a change has been made during LS1 on the users side, the concerned connection with the BIS must be re-commissioned. • Why during LS1? • The commissioning has to be done before the machines restart • Risks / impact if not during LS1 • Problem receiving user permits → Problem for Machine Protection • Time period • Before August 2014 • Manpower • Christophe and Spyros • Contributions from the other groups • All equipment systems who will make changes • Potential showstoppers • Late information about the modification of a user system • It implies the participation of people from each user system

  10. 7 – BIS and SMP : Individual Test Systems (#11658 and #11659) • Description of the activity • Individual System Test for the BIS and SMP system prior to beam operation • It regroups pre-operational checks and automatic CIBU tests • Why during LS1? • The tests have to be defined and performed before the machines restart • Risks / impact if not during LS1 • Malfunction of BIS or SMP (with all the consequences) • Time period • Before August 2014 • Manpower • Stéphane and Christophe • Review and transmit specs to MS • Contributions from the other groups • None • Potential showstoppers • BIS new hardware / new VHDL / new FESA class…

  11. 8 – BIS Collaboration : LBDS improvement (#12054) • Description of the activity • Connect the LHC BIS to the LBDS re-triggering system (so called 3rd channel). • This channel is directly connected to the LBDS to provoke asynchronous dump in case the TSU doesn’t trigger the expected synchronous beam dump • It implies a new CIBG card (Beam Permit Loop Generator) • The CIBG 3rd channel should reach a high availability level • Why during LS1? • It has to be done for the restart of the LHC • Risks / impact if not during LS1 • Beam potentially not dumped → Pbfor Machine Protection • Time period • Before August 2014 • Manpower • Stéphane • MS: Follow-up for FESA, Java GUI and PM data integration • Collaboration for the other groups • TE-ABT • Potential showstoppers • None Asynchronous DumpingS Beam permit loops

  12. 9 – BIS : Specification of BIS v2 • Description of the activity • Specify the functionalities and hardware for the BIS version2 • It will be developed between LS1 and LS2, and installed during LS2 • Why during LS1? • Dedicate enough time for a well defined specification • Risks / impact if not during LS1 • Delay on the BIS2 project • Time period • none • Manpower • Stéphane • Contributions from the other groups • None • Potential showstoppers • None

  13. Summary Thanks !

  14. Spare Slides

  15. Linac4 Masterplan Revised 2012/16 Masterplan, approved by the LMC on 27.6.2012 Start high-energycommissioning (12 MeV) End high-energycommissioning (160 MeV) 1 year reliability run Ready for H- Ready for 50 MeV protons as backup to Linac2 Connection of Linac4 to the PS Booster during LS2 (2017/18)

  16. Proposed new plan – LS1 details LS1 2013: 3 MeV tests Closing RF structures 2014: Commissioning DTL1 (12 MeV) Commisioning DTL2&3 (50 MeV) After LS1 (July-Dec 2014): Closing line for protons Commissioning to 100MeV Note that the 2014 plan canbemodulateddepending on the actual situation with LS1

More Related