I-15 South Design-Build Project

I-15 South Design-Build Project. Tropicana Avenue To Blue Diamond Road. Presented by Susan Martinovich. Presented to Las Vegas Convention and Visitors Authority. Paving the Way to a More Mobile Las Vegas. What is the I-15 South Design-Build Project ?.

yukio
Download Presentation

I-15 South Design-Build Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. I-15 South Design-Build Project Tropicana Avenue To Blue Diamond Road Presented by Susan Martinovich Presented to Las Vegas Convention and Visitors Authority Paving the Way to a More Mobile Las Vegas

  2. What is the I-15 South Design-Build Project? Improvements to I-15 from Tropicana Ave. to South of Blue Diamond Rd., including: • Widening I-15 • Addition of Collector Distributor roads • Improved ramps at interchanges • Tropicana Avenue • Russell Road • I-215 • Blue Diamond Road • Silverado Ranch Blvd

  3. What is the I-15 South Design-Build Project? Improvements to I-15 from Tropicana Ave. to south of Blue Diamond Rd., including: • New bridges over I-15 at Warm Springs Road and Sunset Road • Landscaping and Aesthetics • Intelligent Transportation System • Ramp Meters • Variable Message Signs • Cameras

  4. I-15 South Design-Build Project Russell Rd. 215 Silverado Ranch Blvd. Tropicana Ave. Blue Diamond Rd.

  5. Project Costs Design-Build Lump Sum Contact $246,500,000 Prelim. Engr. (includes procurement) $16,000,000 Construction Engineering $17,000,000 Incentives, Escalations, and Utilities $6,000,000

  6. Schedule Notice to Proceed – September 2009 Design substantially completed – Fall 2010 Construction began – December 2009 All I-15 Lanes completed and open - March 2012 Project Completion – Spring 2012

  7. Project Status • Design - 95% complete • Construction - 48% complete

  8. Budget/CashFlow

  9. Employment Currently 300+/- working on design and construction Peak employment estimated at 400+/-

  10. Construction to Date Southbound I-15 auxiliary lane and 2-lane off ramp to Silverado Ranch Road- Open Northbound I-15 Auxiliary lane from Silverado Ranch - Open Sunset Bridge - Under Construction I-15/I-215 interchange - Under Construction C-D Roads and bridges - Under Construction Russell Road (widening) - Under Construction

  11. UpcomingMilestones • Sunset Bridge • Open January 13 • Warm Springs Bridge • To be demolished Feb 2011 • To re-open as 6-lane bridge Spring 2012 • I-15/ I-215 Construction • To be complete Feb 2012 • Russell Road Widening • To be complete Aug 2011