ILE Project Integrated Logistics Environment Kickoff Meeting

ILE Project Integrated Logistics Environment Kickoff Meeting. Location: Mystic Marriott Hotel Groton, CT Date: Thursday, June 17, 2010 Overview Presented by: Dr. Burton Gischner. ILE Project Overview. Goals Objectives Project Administration Technology Transfer Activities

lenore-king
Download Presentation

ILE Project Integrated Logistics Environment Kickoff Meeting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ILE ProjectIntegrated Logistics EnvironmentKickoff Meeting Location: Mystic Marriott Hotel Groton, CT Date: Thursday, June 17, 2010 Overview Presented by: Dr. Burton Gischner

  2. ILE Project Overview • Goals • Objectives • Project Administration • Technology Transfer Activities • Program Management, Technology Transfer, and Software Development Plans • Deliverables and Milestones • Schedule for Upcoming Meetings

  3. Goals • Tools and Methods for Supporting Next Generation Shipbuilding IPDE (SCIM Evaluation) • This task will demonstrate the capabilities of the NPDI SCIM as the means for supporting the next generation IPDE • Completion of the Ship Common Information Model (SCIM Development) • This task proposes to complete the remaining chapters of the Ship Common Information Model

  4. Objectives • Tools and Methods for Supporting Next Generation Shipbuilding IPDE (SCIM Evaluation) • This task will apply the tools and methods developed by the ISE team to two current shipbuilding requirements: VIRGINIA Class IPDE data migration and sharing of DDG 1000 structural design data with manufacturing systems across shipyards • Moreover, this task will use the NPDI Ship Common Information Model (SCIM) as the basis for these two pilots • As a result, this task will not only benefit current Navy programs but will also demonstrate the capabilities of the NPDI SCIM as the means for supporting interoperability of the next generation IPDE

  5. Objectives cont’d. • Completion of the Ship Common Information Model (SCIM Development) • The Ship Common Information Model (SCIM) was defined as requiring fifteen chapters to specify the requirements for exchange of product model data among shipyards and the Navy. The development of eight of these chapters has been funded through NSRP under the Navy Product Data Initiative (NPDI). • This effort will complete the SCIM and thereby will facilitate the data exchanges to be developed within the Integrated Logistics Environment

  6. Project Administration • Project is administered and led by Electric Boat (EB) • Subcontractors: • Northrop Grumman Shipbuilding (NGSB) • Northrop Grumman Technical Services (NGTS) • Product Data Services (PDS) • Administration will be guided by a Program Management Plan to be developed in the next few weeks

  7. Project Exploder • The Exploder established for the ISE-4, ISE-5, and ISE-6 Projects will continue to be used for ILE • It is entitled: • NSRP–ISE4-l@aticorp.org • In addition, a Bulletin Board remains available under the ISETools.org website • Permits threaded discussions • Automated Registration • Ability to only retrieve messages when desired

  8. ISETools.org Bulletin Board • Accessible from the ISE Tools website • http://www.isetools.org • Click on Bulletin Board • Communicate with other registered members • Automated registration • Create new discussion topics • Reply to existing discussion topics • Include attachments with your message • Receive e-mail notifications of new replies, as desired

  9. Technology Transfer Activities • Updates and Presentations during 1st Year • Project Updates will be given at each System Technology Panel Meeting • Next Meeting: Washington, DC Sept. – Oct. 2010 • Following Meeting: New Orleans, LA Dec. 2010 • Presentation at: Ship Production Symposium • Bellevue, WA November 3-5, 2010 • Possible Presentation at: ShipTech 2011 • Biloxi, MS March 15-16, 2011

  10. Program Management PlanTechnology Transfer PlanSoftware Development Plan • These three deliverables will guide the execution of the project • Will be completed and delivered by June 30, 2010

  11. Deliverables and Milestones • Each of the two tasks will have a set of Deliverables and Milestones at the end of each Quarter, and there will be a Wrap-up Meeting and Final Report in Washington, DC at the conclusion of Month 12 for the SCIM Evaluation Task (Task 1) and at the conclusion of Month 24 for the SCIM Development Task (Task 2) • There will also be a Business Status Report and a Technical Status Report issued as a Deliverable at the end of each Quarter • The list below provides a description of the deliverables for each task

  12. Deliverables and Milestones cont’d. TaskMonthDeliverable 1.1 2 Report on Extraction of Piping Data in SCIM Format from VIRGINIA IPDE 1.1 5 Report on Extraction of Structural Data in SCIM Format from VIRGINIA IPDE 1.1 8 Analysis of SCIM Piping & Structural Models vs. Data Needed for VIRGINIA Migration 1.1 11 Final Wrap-up Meeting & Report of SCIM Deficiencies in Piping & Structural and Recommendations 1.2 2 Structural Model Import Requirements Report for DDG 1000 1.2 5 SCIM Gap Analysis Report for DDG 1000 1.2 8 SCIM Dataset Results Report for DDG 1000 1.2 11 Final Wrap-up Meeting & Import Results Report for DDG 1000 2 14 Complete SCIM Chapters for HVAC Functional & Physical Design 2 17 Complete SCIM Chapters for Electrotechnical Functional & Physical Design 2 20 Complete SCIM Chapters for Pipe Stress & Engineering Analysis 2 23 Complete SCIM Chapter for Structural CAM (Lofting & Nesting) 2 24 Final Report

  13. Deliverables and Milestones cont’d. MonthDeliverable 2 1st Qtr Business & Technical Status Reports 5 2nd Qtr Business & Technical Status Reports 8 3rd Qtr Business & Technical Status Reports 11 4th Qtr Business & Technical Status Reports 14 5th Qtr Business & Technical Status Reports 17 6th Qtr Business & Technical Status Reports 20 7th Qtr Business & Technical Status Reports 23 8th Qtr Business & Technical Status Reports

  14. Schedule for Upcoming Meetings • June 2010 – Kickoff Meeting – Groton, CT • Oct. 2010 – Technical/Design Review Meeting – Virginia Beach, VA • Nov. 2010 – Presentation at SPS – Bellevue, WA • Jan. 2011 – Technical/Design Review Meeting – Groton, CT • Mar, 2011 – Presentation at ShipTech 2011 – Biloxi, MS • Apr. 2011 – Team Meeting – Washington, DC • May 2011 – Kickoff Meeting for Task 2 – Groton, CT • Oct. 2011 – Technical/Design Review Meeting – Virginia Beach, VA • Nov. 2011 – Presentation at SPS – Houston, TX • Jan. 2012 – Technical/Design Review Meeting – Washington, DC • Mar, 2012 – Presentation at ShipTech 2012 – Biloxi, MS • Apr. 2012 – Final Team Meeting – Washington, DC

More Related