4th Annual X-band Structure Collaboration Meeting Manufacturing RF structures at CERN

4th Annual X-band Structure Collaboration Meeting Manufacturing RF structures at CERN. G. Riddone, 04/05/2010

shing
Download Presentation

4th Annual X-band Structure Collaboration Meeting Manufacturing RF structures at CERN

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 4th Annual X-band Structure Collaboration MeetingManufacturing RF structures at CERN G. Riddone, 04/05/2010 (contribution from Production Team: S. Atieh, G. Arnau, Ph. De Souza, A. Grudiev, D. Gudkov, T. Katopodis, S. Lebet, M. Filippova, M. Malabaila, A. Olyunin, A. Samoshkin, J. Shi, M. Saifoulina, A. Solodko, I. Syratchev, M. Taborelli, T. Uusimaeki)

  2. Content Scope: RF acceleration structures, PETS and RF components Production flow: accelerating structures and PETS Production program and status Production capability and master schedule Dedicated test program Conclusions

  3. Scope PETS (12 GHz, TBTS) TD24#2 at CERN (12 GHz) TD18#3 at SLAC TD18#2 at KEK Hybrid High-power dry load PETS (11.4 GHz, test at SLAC) Variable high power splitter

  4. Baseline procedure NLC/JLC fabrication technology: validated to 100 MV/m (baseline adopted in 09.2011) Diamond machining (disks, sealed structures) Cleaning with light etch Bonding cycle H2 diffusion bonding/brazing at ~ 1000 ˚C New procedure Vacuum baking 650 ˚C > 10 days Baking cycle

  5. Accelerating structures: baseline manufacturing flow Engineering design and tendering High precision diamond machining QC Machining of couplers Brazing of couplers (H2, 1045 °C, AuCu) Cleaning (light etch)  SLAC procedure Diffusion bonding of disk stack (H2, 1020 °C) Brazing of couplers, cooling, tuning studs (AuCu, 1020-1000 °C) Welding extremity flanges Packaging (N2) and shipping Baking (vacuum, 650 °C, >10 d) RF check and tuning Witness sample for each fabrication step brazing./bonding: 30 mbar H2

  6. Production base program T24 undamped F = under fabrication D = under eng. design F 2010 TD24 damped F TD24 – with wakefield monitors • TD24 R05 KS • reduced DT F D • TD24 R05 KS – reduced DT with damping loads CDR D • TD26 KS • – reduced DT with damping loads • and compact coupler 2011 D CLIC structures with all features and technical systems D

  7. Production program

  8. Production program

  9. Production program

  10. T18 (KS) N2 Under baking  shipping to SLAC on 10.05.2010 Diffusion bonding – 1020°C SEM Inlet inspection Brazing 35Au65Cu – 1021°C/1025°C

  11. T18 (KS) N2 Preparation for baking Preparation for final brazing Flange welding under N2 injection RF measurements

  12. TD24 12 GHZ (TBTS) Machining at VDL Shape tolerance ±2.5 mm New CMM (Coordinate Measuring Machine) under procurement at CERN

  13. TD24 12 GHz (TBTS) Structure installation in the tank and in the CLEX

  14. T18 KS N1 - 11.4 GHz Machining a VDL Shape tolerance ±2.5 mm • Status: • machining of the couplers after brazing • bonding of the disks on 04.05.2010 Brazing 25Au75Cu – 1043°C, H2

  15. T24 C N1 – 12 GHz • Status: • machining of couplers under way • bonding of the structure on 5.05.2010 Diffusion bonding of couplers: 1030-1040°C, H2

  16. Fabrication of PETS at 11.4 GHz with damping material Damping material Bar length ~ 300 mm Shape tolerance within specification: ± 7.5 mm Minitank with bars inside Status: assembly finished Coupler Procedure as close as possible to the baseline, but some difference due to design and infrastructures

  17. PETS: baseline manufacturing flow Assembly of the 8 bars with damping loads Engineering design QC EB welding of the bars QC Cleaning (NGL + solvent) Assembly of couplers-bars and mini-tank Cleaning (NGL + chromic acid) PETS bars Test assembly EB welding of tank Assembly PETS couplers 1st brazing (body), vacuum, 800 C Vacuum test Baking (vacuum, 200 C, 2 h) Now RF check RF check Cleaning (degreasing only) Final bake-out (150 C, 2h) SiC 2nd brazing (flanges, cooling), vacuum, 800 C Pre-fire (vacuum, 1000 C) Packaging (N2) 12.05

  18. PETS 11.4 GHz damping material Bar with damping material Cooling circuit brazing Nickel base – 1030 °C Assembly in the tank Bar assembly

  19. Production capability Firms qualified: • Disks damped: VDL (NL), Mechacrome (FR), Savimex (FR) • PETS: VDL (NL), Unitek (IT), KERN (DE), Comeb (IT) • (effort continues to qualify new firms: DMP (SP), IPK (DE), KERN (DE)) For each structure, at least two units are manufactured (almost in parallel) At present, potential capability up to 15 structures per year

  20. Master schedule

  21. Towards CLIC structures Wakefield monitor Damping material Coupler On-off system • CDR – TD24 R05 SiC.KS • Accelerating structure with all features: damping material, wakefield monitor and technical systems; under eng. design (first structure at the end of 2010). Assembly test with a prototype structure are scheduled in the coming weeks. • PETS with on-off system: under design. On-off system to be tested in Q4, 2010Actuator prototype received on 3.5.2010 • Cost estimate in needed by 2010: launched dedicated studies with three companies/institutes

  22. RF components Several RF components are needed for different test stands

  23. Dedicated program: heat treatment comparison Motivation: understand why bonding under H2 gives the best results (baseline) Test with few samples conducted already in 2009 (before adopting baseline). Some results are shown hereafter Heat treatment - vacuum Heat treatment H2, 30 mbar Decision to pursue the investigation with several samples to increase statistics

  24. Dedicated program: heat treatment comparison Samples under cleaning, results expected by summer 2010 Different heat treatments/atmosphere Different cleaning Different places Ideas are welcome!

  25. Conclusions • NLC/JLC fabrication technology validated for CLIC accelerating structures to 100 MV/m, adopted by CERN (since 09.2009) • First structure built by CERN T18 (high power tests are important): modifications implemented for 2nd structure after visit at SLAC • Important milestone is the TD24 with SiC: first unit ready by end of this year • Production of RF components is expanding • Production capability up to 15 structures per year  higher than available testing slots • A lot of work: involvement of other laboratories to exchange experience and expertise is essential • Industrialization, mass production and cost study launched for few structure configurations