2007 Transmission Summit July 31, 2007 New Orleans, Louisiana. Generation Interconnection Overview. ICT GI Responsibilities. Receive and validate Interconnection Applications Determine if changes are a material modification Provide and execute Interconnection Study Agreements.

blake-may
Download Presentation

Generation Interconnection Overview

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 2007 Transmission Summit July 31, 2007 New Orleans, Louisiana Generation Interconnection Overview

  2. ICT GI Responsibilities • Receive and validate Interconnection Applications • Determine if changes are a material modification • Provide and execute Interconnection Study Agreements

  3. ICT GI Responsibilities • Perform Studies: • Feasibility Studies • System Impact Studies • Optional Interconnection Studies • Coordinate such studies with any Affected Systems

  4. ICT GI Responsibilities • Provide all notices to the customer as required by the Large Generation Interconnection Procedures (LGIP) • Respond to any inquiries by the Interconnection Customer • Maintain, administer, and post a queue for Interconnection Study requests

  5. ICT GI Responsibilities • Review and validate the results of the Facility Study • Prepare the Facility Study Report • Classify upgrades as base plan or supplemental regarding Attachment T to the Tariff

  6. Entergy GI Responsibilities • Provide data and information required to perform the Interconnection Studies • Tender, enter into, and file all Interconnection Agreements • Enter into 3 party Facility Study Agreements with ICT and Customer • Perform Facility Studies

  7. Interconnection Requests • Currently 12 active Interconnection Requests in the queue • The ICT has entered into study agreements for 11 of them • Status • 2 – Set to begin • 7 – System Impact Study • 1 – Facility Study • 1 – IOA execution pending

  8. Contacts Brandon Hentschel 501-688-1603 bhentschel@spp.org Jason Russell 501-614-3514 jrussell@spp.org