180 likes | 192 Views
Join us for the Crescent School District Facilities Planning Meeting to discuss the current and future facility needs of the school district. We will review completed capital projects, discuss current facility considerations, and explore potential solutions for improving our campus. Your feedback is essential in shaping the future of our school's facilities.
E N D
Crescent School District Facilities Planning Oct 9, 2019 6:30 PM- School Library
Agenda • Welcome and Introductions • New District Strategic Plan • Look back: Capital Projects completed since 2016 • Current facility considerations/Campus Tours • Look forward: group discussions of facility needs • Adjourn
Looking Back: 2016 Capital Projects Levy Budgeted: $114,943 Actual: $100,123 Saved: $14,820
Looking Back: 2016 Capital Projects Levy Budgeted: $33,333 Actual: $22,359 Saved: $10,974
Looking Back: 2016 Capital Projects Levy Budgeted: $57,470 Actual: $54,359 Saved: $3,111
2016 Capital Projects Levy Budgeted: $22,989 Actual: $6,485 Saved: $16,504
Looking Back: 2016 Capital Projects Levy Budgeted: $40,230 Actual: $37,040 Saved: $3,190
Looking Back: 2016 Capital Projects Levy Budgeted: $22,989 Actual: $25,502 Exceeded Budget: $2,513
Looking Back: 2016 Capital Projects Levy Complete Budgeted: $108,046 Actual (to date): $48,524 Left to Spend: $59,358
Looking Back: Summary 4-year levy: $400,000 (Levy Rate $0.27-0.31 per thousand) ($100,000 per year) 93% of Projects Complete 100% On Time 100% Overall Under Budget
Current Facility Needs Band Room Ceiling Tiles need replacing, Overall updating needed Backup Generators: Needed for Café/Kitchen in case of long term power outage & Septic System • Cafeteria: • Ceiling Tiles need replacing • Bathrooms need remodeling • Overall updating needed • Locker Rooms: • Remodeling Needed for Safety & Privacy • Kitchen: • Dishwasher needs replacing • Counters, Floors, Walls need upgrading • Gym: • 1970’s Electrical Panel Needs Replacing • Gym Foyer Needs Upgrading • Concessions needs water, sink for health & safety, overall upgrade Playground Remove wood chips & replace with padding Play Shed / Press Box Roof needs replacing Critical Safety Upgrades • Technology: • Security cameras needing upgrade & more of them
Current Enrollment Trends More kids = Greater Spatial Needs
Current Facilities Constraints • ELEMENTARY • Temporary walls make it very difficult to upgrade technology & improve sound. • Bathrooms need upgrading • Technology needs • Desire for common area PORTABLES 1980-era, were meant to be temporary solutions for space but have outlived their expiration date…very inefficient and expensive to maintain • CENTRAL OFFICE • Office space needs exceed capacity (using old portables) • Location is inadequate for campus safety/public access • MIDDLE SCHOOL • Classrooms are spread all over campus in “make-shift” manner • Common area needed • STORAGE/ARCHIVING NEEDS • File storage is inadequate and spread in various locations throughout campus • Storage space inadequate for computers, desks, chairs, etc. • HIGH SCHOOL • Space needs becoming more apparent • Common area needed
Looking Forward • How do we? • Be responsible with what we have • Prepare for a competitive future • Keep our property rates affordable
Looking Forward: Long Term Facility Planning PORTABLES Eliminate • CAMPUS SAFETY • Perimeter needs securing • CENTRAL OFFICE • Move to central location WITH access to public • SPECIAL ED SPACE • Space needs becoming more apparent • Common area needed • ELEMENTARY • Fill in “hole”, gut, rewire building with modern facilities & wiring • CTE SPACE • For training students in trades such as metal, wood, and agricultural • TRANSPORTATION CENTER • Provide area to house district vehicles • MIDDLE SCHOOL • Provide centrally-located, modernized learning space • STORAGE/ARCHIVING NEEDS • Discover adequate storage location • HIGH SCHOOL • Provide Expanded, Modernized Learning Space
Looking forward… What do you see for our school’s future?
Please give us a little feedback by responding to a short survey