nTof Civil engineering Status -5 July 2013. EDMS approval procedure for « Execution drawings » launched on 24/05/2013. Drawings approved on 10/06/2013
E N D
nTof Civil engineering Status-5 July 2013 • EDMS approvalprocedure for « Executiondrawings » launched on 24/05/2013. Drawingsapproved on 10/06/2013 • CERN preparatory works (antennas removal, radio club barrack removal, asbestos removal B559, deviation of the optical fibre, power and water temporary supply for the worksite) finished on 30/04/2013 • Contractor’s main works started on 13/05/2013: Done: • Worksite installation • Demolition of barrack 559 • Deviation of the existing networks • Earthworks • Beam shaft and opening ɸ80 in the roof of the nTOFtechnical gallery • Piles Ongoing: • Concreting of the building foundations on the ISR slab L.A.Lopez
Désamiantage Dépose baraque du Radio-club
Terrassement Cérémonie 1er coup de pelle
Puits du faisceau Carottage faisceau dans galerie nTOF
Puits fini du faisceau Déviation des réseaux
Nextsteps • Concretingworks → September 2013 • Finishingworks (waterproofing, insulation, doors, « chape », painting) → October-November 2013 • Landscaping → November 2013 L.A.Lopez