1 / 15

PIP Update

PIP Update. Aug 6 th 2012. Agenda. Summary Update Current Activities Bill Pellico – N Eddy - Linac BPMs. Update. General Info Current Work Booster RF cavity 5 now being refurbished (putting on tuners)

ekram
Download Presentation

PIP Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PIP Update Aug 6th 2012

  2. Agenda • Summary Update • Current Activities • Bill Pellico – • N Eddy - Linac BPMs

  3. Update General Info • Current Work • Booster RF cavity 5 now being refurbished (putting on tuners) • Linac Transformer – Plant visit today by EE support, still working out details of install • Booster temp transformer installed – new one in 8 – 9 months • LCW – Work Continues – looks to be on schedule • RFQ – beam tests continue – next slide • REPORT for High Power – Preparing for submission to Directorate for approval • High Power Ferrite Testing - 5KW amp test done on old ferrite – still no notable lose? • Booster Absorber – absorber on aisle and parts being machined – • Linac Modulator – Testing at 7 for DTI • Modulator – SLAC will be in on Aug 27 to discuss their work • Booster Modulators – Aug. schedule says we should see have of Mods completed? Shutdown - comments (Fernanda, Todd, Mary)? PIP PMG August 2nd – Went well – a lot of details • TOPIC Presenter Time Description • Introduction/Management Pellico 20 Minutes History, goals and guidelines • Linac Fernanda 20 Minutes Linac (tasks, milestones/goals) • Booster Keith 20 Minutes Booster (tasks, milestones/ goals) • RLS/Project Controls Elmie 15 Minutes RLS schedule – base line/update(s) • Budget Constraints Bob 15 Minutes Budget and targeted goals issues

  4. FY12 Budget (~84% of FY) Look at Task funds – make sure you as managers know what the balance is!!

  5. Work still needs to be done on: Vacuum Testing Second Source LEBT Stand mechanics – slide Einzel Lens trigging MEBT stand – not yet received Vacuum – Argonne Gas Simulations – flatness question Extractor second supply Extractor Safety Switch • Testing of RFQ – Schedule • Emittance Measurements • This week • RF Bunching Measurements • Maybe end of week – or early next • Run at operational level for a week • Review Schedule • Declare Start Date

  6. Absorber Pics

  7. Talks • N. Eddy - Linac BPMs • D. Barak - High Power Testing

  8. Linac/400 MeV BPM System StatusNathan EddyPIP Meeting8/8/12

  9. Production Board Status (6/6/12) • Received first fully stuffed production board before shutdown for checkout • Found error in PCB • Require remaking 80 PCBs • Delay Assembly • $5k additional cost • $10k additional cost due to parts • 10 Additional boards + Prototypes • New PCBs in production • Assembled boards ~1 month

  10. Production Board Status • PCB manufacturer had issues with first run, boards failed testing • Lost their production line manager • They had to re-run the boards – 6 week delay • PCB boards are now complete & tested and were all delivered to the assembly house • Expect first golden sample from assembly house by next week

  11. Production Board Status Cont’d • Plan thorough checkout of the golden sample before releasing • Will include installing in LE Linac • Once released assembly of all boards will be complete in 4 weeks • Expect all boards delivered by mid September • Boards will be bench tested then can be installed • Will start with LE Linac • If feasible, all boards could be beam tested in LE Linac before installation elsewhere

  12. LE Linac Beam Tests • Work underway to instrument bpms (2H, 2V) from tank 3 with new electronics • Electronics installed last week (prototype) • ACNET device conversion underway • Will install golden sample when available • Expand to include all LE bpms which see beam during NTF running

  13. Software Status • Provide average Position, Intensity, & Relative Phase over each beam pulse for every BPM @15Hz – in ACNET via linac controls • Have an OAC to perform setup and control • Read/Write all control registers • Synchronized waveform readback • Position, Intensity, Phase @3MHz • Calibration control • Basic functionality tested

  14. 400 MeV Line Software • Current 400 MeV Line bpms use different electronics, readout, and application software • Had several meetings to discuss options • Plan is to extend Linac Controls readout to these bpms • Existing front-end vme processors will be used • Readout structure will be tweaked to support existing 400 MeV BPM applications

  15. Plan • Complete conversion of LE Linacbpms to new system • Network connections done • Need to provide 805MHz • Replace these boards with Production boards once available • Will replace the rest of the crates as Production boards become available • Driven by board checkout • May rotate them through LE section for beam checkout • Expect all new boards installed early next year

More Related