1 / 24

BNL ERL Cryomodule

BNL ERL Cryomodule. Andrew Burrill ERL 2007. What is it, and why are we building it?. ERL prototype is a test bed for the RHIC II upgrade High current design 0.5A 1.4 nC/bunch as well as 5 nC/bunch 54 MeV RHIC II State of the art accelerating cavity, injector and novel injection scheme

floyd
Download Presentation

BNL ERL Cryomodule

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BNL ERL Cryomodule Andrew Burrill ERL 2007

  2. What is it, and why are we building it? • ERL prototype is a test bed for the RHIC II upgrade • High current design 0.5A • 1.4 nC/bunch as well as 5 nC/bunch 54 MeV RHIC II • State of the art accelerating cavity, injector and novel injection scheme • Real high current photocathode choices • Custom laser system What the cryomodule needs to deliver • High current acceleration while avoiding beam breakup • Ensure all HOM’s are carried to the load • Provide good accelerating gradient • Reduce sensitivity to acoustics A. Burrill ERL Workshop, 2007

  3. ERL Layout A. Burrill ERL Workshop, 2007

  4. Courtesy Doug Holmes A. Burrill ERL Workshop, 2007

  5. Cavity String assembly Courtesy Doug Holmes A. Burrill ERL Workshop, 2007

  6. Cryomodule interface Courtesy Doug Holmes A. Burrill ERL Workshop, 2007

  7. Schedule • Weld He vessel and assemble string Q3 07 • Assemble to space frame and ship to BNL Q3 07 • Install all remaining instrumentation, shielding, vacuum vessel install in 912 Q3 07 • Begin cold emission testing Q4 07 A. Burrill ERL Workshop, 2007

  8. Cavity Parameters Courtesy Ram Calaga A. Burrill ERL Workshop, 2007

  9. Design benefits • No trapped HOM’s • Very high BBU threshold, > 1.8A • 24 cm water cooled Ferrite absorbers capable of 12 kW HOM power A. Burrill ERL Workshop, 2007

  10. Cavity Mechanical Stiffness A. Burrill ERL Workshop, 2007

  11. Cavity stiffness A. Burrill ERL Workshop, 2007

  12. Tuner Courtesy Jim Rank A. Burrill ERL Workshop, 2007

  13. Fundamental power coupler A. Burrill ERL Workshop, 2007

  14. Activity Summary • Cavity designed by BNL and fabricated by AES • Cavity baseline measurements were made at AES, then cavity was shipped to JLAB for processing • Physical dimensions of the cavity made processing a challenge and several new things were learned • Initial cavity performance was less than expected so several R&D efforts were undertaken to reach our target gradient • Cavity is now ready to have He vessel welded on and one more VTA pass made prior to assembly into the cavity string for shipment back to BNL A. Burrill ERL Workshop, 2007

  15. Processing summary • Initial cavity performance was less than expected • End-flanges were modified to eliminate heating, this greatly improved performance • He processing was subsequently used to help improve performance • Final improvements came from a low temperature 110°C vacuum bake A. Burrill ERL Workshop, 2007

  16. Initial Cavity Performance A. Burrill ERL Workshop, 2007

  17. Effects of Helium Processing A. Burrill ERL Workshop, 2007

  18. Benefits of a low temperature bakeout at 110 degrees A. Burrill ERL Workshop, 2007

  19. Indium contamination • Compromising an indium seal while baking a cavity is not the end of the world, and performance can be easily recovered • Cavity was cleaned by flowing conc. Nitric acid for one hour • Nitric dissolves indium but does nothing to Nb, unlike BCP which etches Nb at a much faster rate than indium A. Burrill ERL Workshop, 2007

  20. High pressure rinsing does not have to be done in a cleanroom, it probably should be but…. • Our HPR system was configured in the chemistry room with a N2 gas purge. • Cavity exhibited no field emission after several passes through the HPR system A. Burrill ERL Workshop, 2007

  21. Low temperature bake-out offered significant improvement • Cavity was placed in a bake-out box and mounted with 7 thermocouples to ensure uniform heating A. Burrill ERL Workshop, 2007

  22. Other techniques that could be attempted • High Temperature post-purification bake at 1300 C in presence of Ti to improve RRR as well as anneal and recrystalize cavity, increase crystal size and help eliminate high field Q slope. • Electro-polish, remove surface roughness, increase gradient by reducing local heating A. Burrill ERL Workshop, 2007

  23. Conclusion • The cavity has reached a very high level of performance, 20.5 MV/m, with low field Qo of 4.5e10 • Assembly into a cryomodule is progressing nicely • Cold emission testing should begin fall of 2007 with a complete ERL in early 2009 A. Burrill ERL Workshop, 2007

  24. Acknowledgements Ilan Ben-zvi, R. Calaga, H. Hahn, V. Litvinenko G. McIntyre, H. Hseuh, C. Pai, D. Phillips, K. Smith, A. Zaltsman AES D. Holmes, M. Cole, A. Favale, J. Rathke, T. Schultheiss JLAB P. Kneisel, R. Rimmer, L. Phillips, J. Prebel, J. Mammoser, J. Saunders ORNL R. Campisi, K Yong Many many others I forgot to mention Supported by DOE/NP, BNL directors office, JTO, ONR A. Burrill ERL Workshop, 2007

More Related