E-Tag Issues Work Group Report 8/15/12

E-Tag Issues Work Group Report 8/15/12. Lisa Wildes Gila River Power LLC. E-Tag Issue. Source BA denying curtailments done 10 mins in the past Have their system set for 5 mins Feel following INT-010-WECC-CRT-2 violates NAESB standards in regards to inadvertent and reliability timelines

gaenor
Download Presentation

E-Tag Issues Work Group Report 8/15/12

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. E-Tag Issues Work Group Report8/15/12 Lisa Wildes Gila River Power LLC

  2. E-Tag Issue • Source BA denying curtailments done 10 mins in the past • Have their system set for 5 mins • Feel following INT-010-WECC-CRT-2 violates NAESB standards in regards to inadvertent and reliability timelines • They previously brought these issues to the OC but were “ignored” • EIWG recommended that they follow the 10-min rule and submit comments on WECC-0077, which was out for comment at the time

  3. Proposed Guideline for e-Tag Ramp Durations • At April 2012 meeting, ISAS voted to put the proposed guideline out for comment • May 4 – Posted for 30-day comment period • June 26 – EIWG discussed comments via webinar • June 27 – Comments and revised guideline posted for ISAS review • June 29 – WECC notified ISAS that approval items had been posted

  4. Proposed Guideline for e-Tag Ramp Durations • Comments received from the CAISO and Powerex • Compressed tables into one by deleting all of the request types since the ramp durations were the same for all • Added a column in for curtailments since there were exceptions for this specific request type

  5. Proposed Guideline for e-Tag Ramp Durations • Right after posting the revised guideline, this was brought to my attention: INT-011-WECC-CRT-2, Ten Minute Recallable Reserves, posted at http://www.wecc.biz/Standards/Development/WECC-0079/default.aspx states: WR2.  Each Purchasing-Selling Entity and each Source Balancing Authority that activates recallable reserves shall submit a downward e-Tag adjustment that includes each of the following characteristics: 1)    A start time that is no earlier than ten minutes prior to the submittal time. 2)    A default ramp duration of zero. Fix: change default ramp duration in table to 0?

  6. Proposed Guideline for e-Tag Ramp Durations • MOTION: Approve (amended) Guideline for e-Tag Default Ramp Durations

  7. Questions? Lisa Wildes Gila River Power LLC LWildes@entegrapower.com