1 / 22

Floodlights on Over Recreation Ground

Floodlights on Over Recreation Ground. Floodlight Project Team. Parish Plan Recommendations 7.13. Over should develop a Local Sports Development Plan OCA should consider ways to increase the availability of outside facilities after daylight hours. Parish Council led Sports Development Group .

judah
Download Presentation

Floodlights on Over Recreation Ground

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Floodlights on Over Recreation Ground Floodlight Project Team

  2. Parish Plan Recommendations 7.13 • Over should develop a Local Sports Development Plan • OCA should consider ways to increase the availability of outside facilities after daylight hours

  3. Parish Council led Sports Development Group • Local Sports Development Plan • To co-ordinate the delivery of projects highlighted in the Plan • To consult with OCA, clubs and community • Set up working groups for project delivery • Reports to Parish Council • No budget

  4. Parish Plan achievements so far Sports and recreation: Chapter 7 • New AWS at Community Centre in use • Refurbishment of Pavilion on Green • New cricket square on Rec. • Drainage on Green financial arrangements agreed • Additional land - negotiations started • Feasibility Study for floodlights in draft

  5. Feasibility Study Project Team • Core Group People with a track record of delivering village community projects • OCA and PC representation • User representation • Advisors Football Association and Highlights Ltd

  6. Benefits • Parish Council • Delivery of another Parish Plan project • OCA • Increased availability of outdoor facilities • Potential for provision of evening external events in line with existing licensing framework • Potential for increasing revenue streams

  7. Benefits • Over Sports FC • Can delay winter kick-offs to 3pm • Improved flexibility for mid week fixtures • Help achieve promotion ambitions • Retain players • Increase the number of home fixtures – Cambs Invitation Cup

  8. Benefits • Over Vets FC • Increased flexibility for fixture arrangements • Opportunity to extend community and charity fundraising activity

  9. Benefits • Cambs Football Association • Current under supply of floodlit pitches • Potential for Over to host County representative games • Over as a football “Centre of Excellence”?

  10. Options • Senior football pitch only • Senior football pitch and training area • Full lighting

  11. Senior Football Pitch • FA standards – category F • 6 masts – 4 at 15 metres high and 2 at 18 metres high • Cost £42,210 ex VAT • Power 38.21kw @12p/hr = £4.60/hr • Removable perimeter safety fence 1 metre high c. £10,000

  12. Add Training lights • Lower standard of lighting • Protects Senior pitch from training use • Independent switching of lights • Cost £7,760 ex VAT • Power 12.74kw @ 12p/hr = £1.50/hr

  13. Full lighting • 2 additional 15 metre high columns • Provide for full matches to be played on Colts pitches • Provide for floodlit cricket (breaking new ground) • Independent switching of lights • Cost £14,775 • Power 12.74kw @ 12p/hr = £1.50/hr

  14. Electricity Supply • Community Centre at full capacity • Connect to grid. EON estimate £ Running cost 12p/hr • Diesel Generator £12,000 ex Vat. Limited life. Maintenance and running costs extra. Security, safety and noise issues. • Renewable energy. Controversial, untested technology in this application, noisy.

  15. Running costs • Electricity consumption 12p/hr • Biennial electrical testing (mandatory) £175 per year • Insurance (discretionary) £350 per year • Replacement lamps £750 (life of 2000 hrs – self cleaning) • Benchmark rental is £50 - £55 for football pitch hire.

  16. Environmental Issues • Light pollution • Visual intrusion • Noise

  17. Risks • Under use or no use of facility • Lack of pro-active action by OCA and users to take advantage of new opportunities to increase use of floodlight facilities

  18. Planning issues • Light pollution • Dazzle traffic? • No protected trees removed • Noise • Complaints about proposal • Floodlighting Curfew

  19. Financial Model • South Cambs District Council 45% • Other grant aiding bodies 45% • Community 10% (ie users fund-raising and their sponsors) • No funding from Parish Council or OCA anticipated unless stipulated as a condition of grant • Running costs, including maintenance, to be met by users through hire fees

  20. Conclusions • Feasible project • Expensive • Achievable subject to funding and Planning • Capable of staged implementation • Creates opportunity for new uses for the Rec. • Project team to become Implementation Team

More Related