PHOS progress in LS1 Alexander Vinogradov 11 August 2014
Work done since 28.07.2014 See PHOS LS1 planning: https://twiki.cern.ch/twiki/pub/ALICE/PhosSRU/PHOS_LS1_schedule-20140513.pdf • Modules M2 and M3: • - Transported to P2 July, 31
Module M1: • - Lab test is over • https://twiki.cern.ch/twiki/pub/ALICE/PhosSRU/0802_Module1_Commissioning.pdf • - Moved to B-167 store area, need the air-tightness test • (The test is planning for end of August, Yannick) • Module M4: • - Moved to testing area. • - Readout test of opened module in progress. • Cooling station: • - Lab test is over. • - Transported to P2 and installed to UX25 August,5:
Work at P2 • Cable trays installing in progress. • Fixation trays production for ethernet cables in progress. • Additional power cables laying for PHOS/DCAL STU modules in progress. • LV cables from Patch panel to PHOS modules is planning nearest time. Note: Updates on SRU/STU/TRU problems and common firmware development for PHOS/EMCAL/DCAL to be discussed at 18.08.14