An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SVHS Construction Update March, 2009

  2. March, 2009 • Placement of Construction office portable by baseball field • Begin site preparation in pool area • Disassemble existing Press Box

  3. April, 2009 • Begin construction of new Press Box • Start excavation work for Ag Barn • Begin construction of new parking areas • Pool and stairs on back of existing gym

  4. May, 2009 • Begin Construction on new Ag Barn • Continue construction on Press Box • Continue construction on new parking areas

  5. June, 2009 • Continue construction on new parking areas • Continue construction on new Ag Barn • Continue construction on Press Box • Start construction on main water line from CLWS

  6. Safety Measures … • each construction worker will be registered to be on site, wear a hard hat with a registration sticker, and a colored site specific vest • construction workers will be subject to background checks • school community and construction workers will be segregated

  7. Online map