An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. August 27, 2012 CTA North Main Line (Red Line) Station Rehabilitation Project 48th Ward – Alderman Harry Osterman

  2. Agenda • Existing Conditions • Project Overview • Public Impact • Q & A

  3. Trackwork & Viaducts

  4. Platforms & Stationhouses

  5. Project Overview • Trackwork: • New waterproofing and drainage system • New track in area of viaduct • Repair concrete trackbed and wall • Viaducts: • Concrete repairs to station viaducts • Painting/coating in viaduct areas • New, brighter lighting under viaducts • Platforms: • Platform deck structure and foundation replacement • Platform fixtures, furnishings, and canopy improvements • New customer communication system • (Excludes Lawrence)

  6. Project Overview • Stationhouses: • New windows, doors and exterior lighting • Exterior tuck pointing • Improved station layouts • New turnstiles • New interior finishes (tile, floor, walls and ceiling) • New signage and interior lighting • Site improvements including sidewalk repairs and new bike racks • Security camera system will be maintained and/or added

  7. Public Impact • CTA Station Closures • Street Closures / Lane Closures • Track Replacement • Viaduct Repairs and Painting • Streetscape

  8. CTA Station Closures

  9. Argyle Station • Station Closure – August 24 – October 5 • Full Street closures for weekend activities • Thursday, August 30, 8:00 a.m. – Monday, September 3, Noon – Platform Installation • Thursday, September 6, 8:00 a.m. – Monday, September 10, Noon – Platform Installation • Thursday, September 20, Noon – Monday, September 24, Noon – Platform Installation • Thursday, September 27, 8:00 a.m.– Monday, October 1, Noon – Platform / Furnishing • Single Lane closures for Viaduct work October 4 – December 28 - East Bound traffic on Argyle will be detoured on Broadway Avenue • to Lawrence if heading north on Broadway Avenue • to Foster if heading south on Broadway Avenue • Other Single Lane Closures • Foster Avenue (nightly) September 4 – September 7, 9 p.m. – 5 a.m. • Foster Avenue September 8, 9 p.m. – 9:00 a. m.

  10. Berwyn Station • Station Closure October 5 – November 16 • Full Street closures for weekend activities • Thursday, August 30, 8:00 a.m. – Monday, September 3, Noon - Trackwork • Thursday, September 6, 8:00 a.m. – Monday, September 10, Noon - Trackwork • Friday, October 5, Noon – Monday, October 8, Noon – Station / Platform demolition • Thursday, October 11, 8:00 a.m. – Monday, October 15, Noon – Platform Installation • Thursday, October 18, 8:00 a.m. – Monday, October 22, Noon – Platform Installation • Thursday, October 25, 8:00 a.m. – Monday, October 29, Noon – Platform Installation • Friday, November 1, Noon – Monday, November 5, Noon – Platform / Furnishing delivery • Single Lane closures for Viaduct work August 20 – October 12 & November 16 – 30 West Bound traffic on Berwyn will be detoured to Foster Avenue

  11. Thorndale Station • Station Closure August 17– September 28 • Full Street closures for weekend activities • Thursday, August 30, 8:00 a.m. – Monday, September 3, Noon – Platform Installation • Thursday, September 6, 8:00 a.m. – Monday, September 10, Noon – Platform Installation • Thursday, September 20, 8:00 a.m.– Monday, September 24, Noon – Platform / Furnishing • Thursday, October 18, 8:00 a.m. – Monday, October 22, Noon – Trackwork • Single Lane closures for Viaduct work October 1 – November 30 East Bound traffic on Thorndale will be detoured on Broadway Avenue • to Bryn Mawr if heading north on Broadway Avenue • to Granville if heading south on Broadway Avenue

  12. Additional Slow Zone Removal • Track Replacement (Full Street Closures) • Granville / Glenlake • Friday, September 7, 8:00 a.m. – Monday, September 10, Noon • Thursday, October 11, 8:00 a.m. – Monday, October 15, Noon • Thursday, October 18, 8:00 a.m. – Monday, October 22, Noon • Bryn Mawr • Thursday, October 18, 8:00 a.m. – Monday, October 22, Noon • Lawrence • Thursday, October 18, 8:00 a.m. – Monday, October 22, Noon (tentative) • TBD • Rosemont • Friday, November 23, 8:00 a.m. – Monday, November 26, Noon • Thursday, December 6, 8:00 a.m. – Monday, December 10, Noon

  13. Questions & Answers