BA5 BEAM DUMP ACTIVITIES FOR YETS 2017-2018. A. Berjillos EN-ACE-OSS 21/12/2017. BA5 Planning. https:// pwa.cern.ch/Projects-Accelerator-Complex-Schedules/Projects.aspx. On delay. BA5 Constraints. Week 51 (21 st & 22 nd Dec). Demi water cut BA5 lift maintenance on 21 st Dec
E N D
BA5 BEAM DUMP ACTIVITIESFOR YETS 2017-2018 A. Berjillos EN-ACE-OSS 21/12/2017
BA5 Planning • https://pwa.cern.ch/Projects-Accelerator-Complex-Schedules/Projects.aspx On delay A. Berjillos
BA5 Constraints A. Berjillos
Week 51 (21st & 22nd Dec) Demi water cut BA5 lift maintenance on 21st Dec from 10:00 to 12:00 BB5 lift maintenance on 21st Dec from 13:00 to 15:00 Take samples of the concrete base Install scaffolding above the machine Remove partially the shielding of iron blocks From 51697 towards ECX5 Remove metallic stairs Install additional structure for cable trays Install Scaffolding to remove the pump Delivery of platform EN-HE Delivery on delay To be confirmed the date EN-CV EN-EL SMB A. Berjillos
Week 2 (8th to 12th Jan) Demi water cut Magnet campaign all week Remove obsolete CV equipment Remove obsolete EN-HE items Remove partially the shielding of iron blocks Install scaffolding above the machine From 51697 towards ECX5 QD51910 to QF52010 Install cable trays in LSS5- Remove obsolete EN-HE items Remove doors PT51,53,55 Remove the pump Kicker Platform Install the platform Remove obsolete CV pipes EN-HE EN-CV Postponed, depending of material delivery To be confirmed the date EN-EL SMB A. Berjillos
Q’s All comments are more than welcome but please let me know by mail
Who I am LSS5SPS Beam Dump Planning Officer • Aurelio Berjillos Barranco • Facility Coordinator at EN-ACE-OSS • Aurelio.berjillos@cern.ch • Phone: 167850 • Useful link: • The planning is available on: https://pwa.cern.ch/Projects-Accelerator-Complex-Schedules/Projects.aspx A. Berjillos