1 / 12

FS Suspension for Virgo+

FS Suspension for Virgo+. Michele Punturo On behalf of the Thermal noise working group of Virgo+. Scientific Motivation. The reduction of the Suspension thermal noise will improve the sensitivity at low frequency:. Scenarios. Many effects to be considered: Mirror thermal noise (see curve b)

mauli
Download Presentation

FS Suspension for Virgo+

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FS Suspension for Virgo+ Michele Punturo On behalf of the Thermal noise working group of Virgo+

  2. Scientific Motivation • The reduction of the Suspension thermal noise will improve the sensitivity at low frequency:

  3. Scenarios • Many effects to be considered: • Mirror thermal noise (see curve b) • Newtonian Noise (compare curve c and a)

  4. Virgo Commissioning Plan • The Virgo collaboration defined the evolution of the commissioning for the next two years Science Run 1 Science Run 2 Noise hunting Noise hunting ITF Shutdown ITF restart 03 06 09 03 06 09 01/2008 01/2006 01/2007

  5. 2008: Virgo+ upgrade • FS suspension • Huge engineering effort • To upgrade the ITF at the beginning of 2008 a well detailed plan must be defined • VIR-PLA-DIR-4700-109 • 4 tasks: Mechanical Realization of a prototype Control test of the prototype Definition of the mounting procedures Production of the 4 payloads

  6. Task #1 • Realization of a Static payload • Fibre production • O2-H2 facility under completion in Cascina (H.Vocca) • CO2 laser facility in delay (June 2006) • Upper clamp design • New component to be designed to connect the FS fibre to the Steel marionette • Lower clamp design • “Ears”: large experience in GEO within the LSC • Suspend a dummy test mass • In progress in Perugia • Steel Marionette • Similar as much as possible to the current Virgo design • Dielectric reference mass • Eddy current issue • Able to accommodate current Virgo coils • Full payload realization

  7. Task #2 • Mechanical response characterization and control test • Setting up the position sensing apparatus • Virgo “local control” design • New marker design exploration • Setting up the digital control chain • Virgo “local control” design • Error signal calibration and diagonalization + Mechanical TF measurements • Decoupling of the different D.O.F. • Payload control • Virgo “local control” design • Frequency dependent driving matrix to compensate for nasty couplings • Monolithic payload robustness tests

  8. Task #3 Ceramic glue Silicate bonding • Definition and test of the mounting procedures • Mirror preparation procedures • Realization of a new design for magnet glueing. • Direct painting of the markers on the mirror (?). • Spacers bonding before coating (?) • Payload assembling and transportation procedures • Definition of the procedures for payload assembly. • Realization of a test prototype in clean room. • Test of the transport and hanging procedures

  9. Task #4 • Production of the four payload components • Preparation of the four mirrors • Currently three Susprasil substrates are available. They are used as spare of the current Virgo mirrors, but can be coated and used for Virgo+ (one of them must be used as PR because it have a small defect that can reduce the Q). Obviously 3 other mirrors must be produced (2+1 spare). The four mirror for Virgo+ must be coated with the best coating available (in terms of optical and mechanical performances) in such a may to reduce the dissipation due to the mechanical losses in the Tantalum. The possibility to paint the markers (if needed) directly on the coating must be investigated. • Preparation of the four marionette • Defininition of the procedure for marionetta series production: construction, material tests, assembly, mechanical and electrical tests before coupling with the monolithic suspension and reaction mass, storage space and structure • Preparation of the four reference masses • Defininition of the procedure for RM series production: • construction, assembly, mechanical and electrical tests to be performed before coupling with marionetta and mirror, storage space and structure • Assembling of the four payloads • The four payload will be assembled as soon as we are ready to mount them (no storing seems possible).

  10. Infrastructures • To be compatible with the commissioning plan, new infrastructures are needed • Experimental area for the fiber production • Two (or one large) clean room in the 1.5km building • Experimental area for the payload assembling • Time schedule and the success of this operation are related to the quick availability of these infrastructures • EGO is investigating for this large effort • Meeting the 19th of January in Cascina

More Related