I-35E/Maryland Ave. Bridge Replacement Design-Build Project S.P. 6280-353 Industry Kickoff Meeting September 27, 2011. Curt Kallio, Design-Build Program Manager David Herzog, Project Manager. Roles and Responsibilities. Disclaimer.

mignon
Download Presentation

Roles and Responsibilities

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. I-35E/Maryland Ave.Bridge ReplacementDesign-Build ProjectS.P. 6280-353Industry Kickoff MeetingSeptember 27, 2011

  2. Curt Kallio, Design-Build Program Manager David Herzog, Project Manager Roles and Responsibilities

  3. Disclaimer What is discussed today is informational only, meant to assist interested teams in the pursuit of this project. The ultimate contract requirements will be included in the Request for Proposals (RFP). There may be changes between now and the time the RFP is issued and proposal due date.

  4. Design-Build Best Value • Two-Step Procurement Process • RFQ (Request for Qualifications) • RFP (Request for Proposals) • RFQ • Draft posted on September 19, 2011 • Short-List Up to 5 Teams • Addendums and clarifications posted to ftp site • Email notification to those who responded to LOI

  5. Design-Build Best Value • RFP • Issued only to the short-listed teams • Technical Proposal • Alternative Technical Concepts • One-on-One Meetings • Stipends • Price/DBE Proposal • Best-Value = Proposal Price/Technical Score

  6. RFQ Update – Prequalification Changes • The Design Engineer – Roadways shall be employed by a firm on MnDOT’s pre-qualified list to perform Work Type 2.12, Highway Design Level 2 • The Design Engineer – Structures shall be employed by a firm on MnDOT’s pre-qualified list to perform Work Type 3.12, Bridge Design - Level 2 • Removed Bridge Design SPMT Engineer from pre-quals. (Remains a Level - A Personnel in 3.3.1)

  7. Procurement Timeline(Subject to Change) ACTIVITY DATE Issue RFQ September 28, 2011 Short List of Submitters November 4, 2011 Issue RFP November 18, 2011 Technical Proposals due January 18, 2012 Price Proposals due February 1, 2012 Anticipated Contract March 2012

  8. General Project Information • No Co-Housing Requirement • Key Participants to be on project or available as described in RFP • DBE - Goal to be determined • Oversight Contract

  9. Why Design-Build? • Project acceleration • Industry Innovation • Speciality skills required (SPMT’s)

  10. What are SPMT’s?(Self-Propelled Modular Transporters) • Combination of multi-axle platforms • Computer-operated • Pivots 360 degrees • Lifts, carries, sets large/heavy loads • Moves at walking speed

  11. What are SPMT’s?

  12. Why SPMT? • Reduce Traffic Disruption • Improve Work Zone Safety • Improve Quality and Constructability • Increase Contractor and Owner Options • Federally funds on the project stipulate that Accelerated Bridge Construction (ABC) used, specifically SPMT’s

  13. Advertisement

  14. Design-Build Webpage http://www.dot.state.mn.us/designbuild

  15. Project InformationI-35E/Maryland Ave.David HerzogMnDOT Metro DistrictProject Manager

  16. Roadway • Bridge • Drainage • MOT • Geotechnical • Permits • Utilities • Deep storm sewer • Relocate watermain Project Details

  17. Project Partners • MnDOT • City of St. Paul • Ramsey County • Federal Highway Administration • Design-Build Proposers • HNTB – RFP Development • DNR – Pedestrian underpass

  18. Project Goals • Quality • Encourage innovative design & construction practices • Design and construct a quality project with quality personnel • Schedule and Budget • Project completion by December 2012 • Stakeholder Satisfaction • Implement effective use of SMPT during construction • Minimize traffic disruptions • Minimize impacts to residents and businesses • Safety • Employment Opportunities

  19. Questions ? • Curt Kallio • Design-Build Program Manager • David Herzog • Project Manager