An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Long-Term System AssessmentTransmission Analysis Update Warren Lasher Regional Planning Group

  2. Purpose • To Inform Near-Term Planning with Potential Solutions that Meet Long-Range System Needs • Intent is not to select new circuits to recommend • Rather, the intent is to provide a selection of alternatives through scenario analysis that can be considered when developing solutions for near-term congestion or reliability needs • To meet the NERC TPL Requirements for development of 10-year transmission plan Regional Planning Group

  3. Specific Focus – LTSA Transmission Analysis • A network simplification tool has been implemented and is being used for the Long-Term System Assessment transmission requirements analysis • The focus of the LTSA is to identify: • Long-Lead-Time Projects – projects that may require 5 or more years to bring on-line • Large Projects – short-term analyses tend to focus on short-term solutions. A long-term perspective can indicate larger projects that both solve short-term issues but also meet long-term system needs more cost-effectively. • This network simplification tool will provide a starting point for larger DOE study Regional Planning Group

  4. After Simplification • Bus count reduced 6,000  3,000 (approx) • Line count reduced 6,000  3,000 (approx) • Flows on 138-kV and 345-kV bulk transmission network mostly unchanged. • Simplified case has similar N-1 behavior (branch loading and voltages) as full case. Regional Planning Group

  5. LTSA Reliability Analysis Overloads 345 kV 138 kV • Overloads after simplification and redispatch. Regional Planning Group

  6. LTSA Reliability Analysis: Houston Overloads 345 kV 138 kV Regional Planning Group

  7. LTSA Reliability Analysis: DFW Overloads 345 kV 138 kV Upgrades being evaluated near Roanoke and Hicks Regional Planning Group

  8. LTSA Reliability Analysis: Valley Overloads 345 kV 138 kV 8255 HAMILTN4 138 8264 EP.H TP4 138 1 Regional Planning Group

  9. LTSA Reliability Analysis: Voltage Analysis • Added 2,000 MVAr of switched capacitors to Houston area • At Zenith and Kind; others more internal to the city.  • 400 MVAr added in Dallas • 200 Mvar at Kendal. Locations for low voltage excursions shown in light green Regional Planning Group

  10. Economic Analysis • Four scenarios are being considered as part of this LTSA: • Business as Usual: Regulatory and market conditions continue in the next ten years as they are today • Low natural gas price: future generation expansion is gas fired. • High natural gas price: Future generation consists of coal and wind generation • High renewables: New generation consists of wind, solar, geothermal and biomass • Generation in each scenario is being added in likely locations. No thermal generation is being added in non-attainment zones. Economic transmission projects are being identified. Regional Planning Group

  11. Summary • LTSA reliability analysis is nearly complete. ERCOT is working with TSPs to review the results. • LTSA economic analysis is in progress, however no projects have yet been identified. • Stability implications of the reliability case is being reviewed. • Results will be included in the Constraints and Needs Report completed by the end of December. Regional Planning Group

  12. Questions? Regional Planning Group