An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Merit Network BTOP Status Robert Duncan & Pete Miller Director of Network Operations

  2. REACH-3MC Project • $130 MM Project • $102 MM Federal Government • $8 MM Merit • $20 MM Commercial Sub-recipients • ~2300 miles of backbone fiber-optic cable • Equal access to Information throughout Michigan • Over 100 schools/libraries directly connected • Fiber is a possibility for hundreds more • Homes and businesses served by sub-recipients and their customers

  3. REACH 3MC Route Breakdown • Round I Routes are in four corridors: • Southern Corridor, Monroe to Benton Harbor • Western Corridor, Benton Harbor to Mackinaw City • Central Corridor, Mount Pleasant to Hillman • Eastern Corridor, Midland to Oscoda • Within each corridor fiber segments from city to city were defined • Intermediate cities were selected for “drive by” to allow future service to under served areas

  4. REACH 3MC II Route Breakdown • Round II Routes are in three corridors: • Middle Corridor, Grand Rapids to Oscoda • North East Corridor, Oscoda to Mackinaw City • Northern Corridor, St. Ignace to Ironwood • Additional spurs from the main path: • Green Bay spur, connects to Wiscnet and BOREASnet • Duluth spur, connects to BOREASnet • Houghton spur, connects to MTU

  5. REACH 3MC, II and Existing Merit Backbone • Merit’s existing 1,600 mile fiber network is shown in GREEN • Round I ARRA funded new build is shown in BLUE • Round II ARRA proposed new build is shown in RED • Both join current Merit fiber network in key locations • Monroe • Hillsdale • Mt. Pleasant • Muskegon • Midland • Hillman • Big Rapids • Grand Rapids

  6. REACH 3MC Network Specifications • Backbone network varies from 60 to 156 count across the entire primary footprint • Distributed across ?? partners • Partners have ownership of various count of fiber on a per segment basis • Lateral builds into Anchor Tenants will be fewer fiber • Builds into Anchor Tenants off of the main fiber trunk are budgeted separately from the backbone • Merit is taking 12-18 count across the segments • On one portion of the Southern Route Merit has 12 count • SMF-28e or equivalent fiber will be used • Low loss across DWDM bands • Reasonable price point • No special optronics required

  7. Fiber Utilization Planning • Merit will immediately light two pair of fiber • One fiber pair will be lit with long haul DWDM 10ge electronics and connect major sites • Approximately 150 to 200 miles apart • No mid segment node insertions planned • The second fiber pair will be lit with CWDM 1ge electronics • This will be the access network • Many mid segment insertions planned • Driving signal both directions to nearest 10g node • Remaining dark fiber will be available for future network expansion and lease 10g North Node 1g Mid Node 1g Mid Node 10g South Node

  8. Implementation Strategy • Completed Environmental Assessment For Round I • Completed Engineering For Round I • Sourced the optical networking HW to ADVA • Completed Round I Construction RFP • Will Work With 5 or 6 Construction Firms • Approximately 20 Construction Crews Running • Build Out From Existing Network

  9. Collaboration • Duluth Spur Connecting To BOREASnet • Green Bay Spur Connecting To Wiscnet and BOREASnet • UW-Extensions (Popular Wis. To Superior) • Build Will Utilize Existing Infrastructure • 20 Miles of Manistee ISD? Conduit • Grand Haven School District Conduit • All Band/ Hillman Conduit • Bridge Authority • Build Collaborations • Bloomingdale Telephone • Northeast Co-OP Duluth

  10. Lessons Learned • Environmental Assessment / FONSI • RFP Everything / Sole Source Justification • Documentation 250000 Docs • Governmental Regulations and Requirements • Permitting • Collaboration Is Critical

  11. Thank You