An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HIFI Mixers HIFI Consortium Meeting 15 April 2003 Wolfgang Wild HIFI Signal Chain Manager SRON Groningen

  2. HIFI Signal Chain (Mixers + IF) • Presentations concerning mixers and IF amplifiers • IF-1 high (4-8 GHz) - Juan Daniel Gallego • IF-2 - Alex Megej • Bands 1 to 4 - Wolfgang Wild • Band 5 - John Pearson • Band 6 - Wolfgang Wild / John Pearson • IF-1 low (2.4-4.8 GHz) - Nick Whyborn

  3. Main points since Oct 2002 • Mixer CDRs were held • Bands 1 to 4: 21/22 Oct 2002 (OK + 7 RIDs) • Band 5: 13 Sep 2002 (OK + RIDs) • Band 6 17 Jan 2003 (OK + 12 RIDs) • QM (FM) fabrication started for bands 1 to 4 (5) • Band 6 collaboration between Chalmers and JPL underway • DMs: bands 1 to 6 delivered • MSA-1 at Chalmers for beam measurements • IF-1 low prototyping (−> Nick) • Updated QM / FM schedule • CPPA parts delivery late: action taken to avoid further delays • Signal Chain Manager full-time on HIFI since 1 Jan 2003

  4. Performance Bands 1 to 5 Input Noise for Mixer + 10 K IF

  5. CPPA FM Parts Delivery Status

  6. Band 1 (LERMA) • Current status • QM parts procurements almost complete; mixer mounting end of April • IRAM delivered ~150 junctions • February/March : extensive FTS testing of IRAM junctions • Noise measurements underway on DM mixer • LERMA FTS operational, LO sources problem • Technical problems : • DM mixer at end of lifetime / slows down measurements

  7. Band 1 FTS + I-V

  8. Band 1 Performance T_rec uncorrected for optics and IF contribution T_IF=85 K (shot noise), limited LO coverage

  9. Band 2 (KOSMA) • QM now in assembly phase • IF bandwidth improvement • Noise temp confirmed • QM horns received • FM horns problematic (quality + schedule) • Issues: QA + schedule

  10. Band 2 Performance Noise temp confirmed with several measurements

  11. QM Band 2 IF Output Bandshift – 200MHz

  12. Band 3 and 4 (SRON) • Status: • Parts for QM arrived, one unit assembled (three more to go) • Intended improvements in QM (EMC, IF): • EMC shielding: OK • IF circuit: resonance within IF band (problem) • Further functional tests OK (magnet, heater) • Performance: • Band 3: receiver ~ 300 K, after correction optics ~ 200 K • Band 4: receiver ~ 400 K @ 1 THz, 300 K after correction • Concerns: • Schedule • CPPA parts • Delivery of flight horns • Resource availability

  13. Band 3 and 4 performance Typical Band 3 results DIMES ground plane, DIMES device Measurement at 4.2 and 2 K. With, without correction for optics losses Recent Band 4 results JPL ground plane, DIMES device Measurement with thick (blue) and thin beam splitter (red) Very promising ! More measurements needed, LO repair needed

  14. Band 6L and 6H (Chalmers / JPL) • DM deliveries from Chalmers to SRON in Sep 02 and Mar 03 • - Interfaces checked, but devices damaged both times • Possible reasons are being investigated • CTH / JPL collaboration underway + challenging • Mixer team is finalizing the fabrication documents package • Optics: under fabrication • Mechanical drawings + circuit boards art works being finalized • EMC test in Feb 03: improvement needed • Chalmers decided to use smaller chips −> more devices / wafer • HEB lifetime test started, first results

  15. HEB mixer performance in DM MU LO: 1.627 THz, TIF= 2-4 K Chalmers The lens was w/o AR coating (30% reflection at Silicon-vacuum interface) The ratio of the mixer-to-LNA noise was about 10dB TNOISE = 1300 − 2100 K

  16. HEB lifetime test • What is HEB sensitivity to atmosphere ? • Chalmers started controlled lifetime test on 3 March • 2 devices in desiccator, 2 devices in lab atmosphere • All devices in ESD safe boxes • Measurements after 1, 16, and 39 days for both • samplesshowed no change in R300 and Ic

  17. QM and FM deliveries • Current best estimates by mixer groups • Assumes CPPA meets user need dates • Assumes no qualification problems

  18. Major worries • QM and FM delivery schedule • CPPA delivery dates for FM parts • FM horn delivery (quality and/or schedule) • If further delays: Funding (Band 2 and 6, IF-2) may • become an issue • Band 6 • Design maturity (EMC compliance,bias and IF boards) • ESD safety • Schedule • Test equipment (LO, beam measurement) • “Surprises” during qualification program • Resources

  19. Summary • CDR for bands 1−6 held • QM (FM) fabrication for bands 1 to 4 (5) underway • Collaborative band 6 effort • Updated QM / FM delivery schedule • First results of HEB lifetime testing

  20. Some Acronyms DM − Demonstration Model QM − Qualification Model FM − Flight Model RID − Review Item Discrepancy CPPA − Central Parts Procurement Agency MSA − Mixer Sub-Assembly HEB − Hot Electron Bolometer LO − Local Oscillator FTS − Fourier Transform Spectrometer QA − Quality Assurance EMC − Electro-Magnetic Compatibility ESD − Electro-Static Discharge